Border infrastructure has become the practical means of asserting territorial claims along the LAC. Critically examine India's progress since 2020 and the gaps that remain.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
India and China have no agreed boundary. On the Line of Actual Control (LAC), whichever side builds roads, tunnels and settlements first holds the ground in practice. China treats frontier development as a long-term duty of the state. Since Galwan (2020), India has moved much faster. But its effort still runs on schemes that must be renewed and is split across agencies.
Progress since 2020
- Connectivity: BRO's allocation rose from ₹6,500 crore (2024-25) to ₹7,146 crore (2025-26). The all-weather Sela Tunnel to Tawang and the Vartak and Arunank projects connect forward areas of Arunachal [1].
- Border villages: VVP-I (₹4,800 crore, 2022-23 to 2025-26) covers 663 northern-border villages and aims to stop out-migration [2]. VVP-II (₹6,839 crore up to 2028-29, fully Centre-funded) extends the programme to the other land borders [3].
- Coordination: a High-Powered Committee under the Cabinet Secretary can relax scheme rules so they work in border areas [3].
- Judicial support: in the Char Dham judgment (2021), the Supreme Court allowed the roads to be widened. It held that courts cannot second-guess the armed forces' infrastructure needs [4].
Gaps that remain
- Land, not money: the Standing Committee on Defence (50th Report) found that land acquisition and slow joint surveys with the states were major causes of delay [5]. A bigger budget does not fix either.
- Renewable, not binding: VVP-I's term ended in 2025-26 [2], and BRO is funded one year at a time [1]. China's commitment does not lapse.
- Silos: the High-Powered Committee covers villages, not BRO roads [3]. Roads and settlements are still planned separately.
- People must choose to stay: China plans and settles its Xiaokang villages from the top. Indian border residents stay only if they can earn a living and get schools and healthcare; out-migration continues [2].
- Ecology is also a security issue: Himalayan road-building raises the risk of landslides. The Court therefore set up the Justice Sikri Oversight Committee to monitor safeguards [4]. A road blocked by a landslide cuts the very supply line it was built for.
India has moved from neglect to momentum, but its border effort still lacks permanence and joined-up planning. The way forward:
- fixed deadlines with the states for land handover;
- multi-year funding guaranteed by law for long BRO projects;
- one frontier plan that covers both roads and villages;
- measuring VVP by how many households stay, not by money spent;
- ecology-sensitive design, following the Char Dham oversight model.
India should copy China's permanence, not its power to override safeguards. That would secure the LAC while keeping federalism and SDG 15 (life on land) intact.
Sources
- 1PIB: Border Roads Organisation briefing document (Jan 2026)BRO budget figures; Sela Tunnel; Vartak and Arunank projects; annual allocation
- 2PIB: Cabinet approves Vibrant Villages Programme for FY 2022-23 to 2025-26 with Rs 4,800 croreVVP-I outlay, 663 villages, out-migration goal, scheme term
- 3PM India: Cabinet approves Vibrant Villages Programme-II for FY 2024-25 to 2028-29₹6,839 crore Central Sector Scheme; other land borders; High-Powered Committee under the Cabinet Secretary
- 4Supreme Court of India: Char Dham highway judgment, 14 Dec 2021road widening allowed for defence needs; Justice A.K. Sikri Oversight Committee
- 5PRS Report Summary: Provision of all-weather road connectivity under BRO (Standing Committee on Defence, 50th Report)land acquisition and joint-survey delays