Cost and time overruns continue to plague Central infrastructure projects despite digital monitoring. Examine the role of platforms like PAIMANA in improving project outcomes.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →MoSPI's monthly Flash Report tracks Central Sector projects costing ₹150 crore and above. In September 2026 it covered 1,853 projects worth ₹37.56 lakh crore, of which only 47.21% of cost had been spent [1]. Digital platforms like PAIMANA have made these projects easier to see, but seeing a delay does not by itself fix it.
Role of PAIMANA in improving outcomes
- Single repository: PAIMANA (September 2025) replaced the legacy OCMS-2006. PAIMANA-CRIP (July 2026) replaced DPIIT's IPMP as the national data layer [2].
- Near-real-time data: About 80% of data now flows through APIs, cutting delays from manual entry [1].
- Integrated metrics: Physical and financial progress are read together. Upfront spending in early stages and pending bills near completion show where a project is stuck [1].
- Sectoral diagnosis: Coal's low expenditure ratio (27.50%) against Water & Sanitation's 70.81% flags slow-moving sectors [1].
- Transparency: Monthly public releases and a Performance Monitoring Dashboard (April 2026) allow time-bound reviews [2].
Why overruns persist
- Root causes are on the ground: Land acquisition, forest clearances and contractor disputes cannot be solved through a dashboard.
- No power to enforce: IPMD's mandate comes from the Allocation of Business Rules, 1961, not an Act. It can publish data but cannot penalise ministries [3].
- Self-reported data: Line ministries report their own progress, and APIs pass on errors faster. MoRTH alone accounts for 53% of projects [1].
- Hidden overruns: Spending is measured against the latest revised cost, so upward cost revisions do not show up in the headline ratio [1].
- Unexplained exits: Projects fell from 1,981 (April 2026) [4] to 1,853, with no split into completed, dropped or migrated.
Way forward
- Publish original and latest cost, plus the number of delayed projects, in every release.
- Send PAIMANA red flags straight into PRAGATI reviews. Overlay delays on PM GatiShakti's GIS map to target land and clearance bottlenecks.
- Have the CAG test-check a sample of self-reported entries each year.
- Publish a reconciliation note for the IPMP-to-CRIP migration.
PAIMANA has moved project monitoring from periodic paperwork to near-real-time e-governance. This is necessary but not sufficient. Linking its data to accountability through PRAGATI, CAG audits and open reporting of overruns can turn visibility into timely delivery. That would advance SDG 9 (resilient infrastructure) and the constitutional ideal of accountable public spending.
Sources
- 1PIB, Monthly Flash Report on Central Sector Infrastructure Projects, September 2026project count, cost, 47.21% spent, API share, physical vs financial progress, sector ratios, MoRTH share, self-reported data
- 2PIB Factsheet on PAIMANA / PAIMANA-CRIPPAIMANA replacing OCMS-2006, CRIP replacing IPMP, Performance Monitoring Dashboard
- 3MoSPI IPMD, About IPMDAllocation of Business Rules mandate, ₹150 crore threshold
- 4PIB document, Flash Report (April 2026 data)1,981 projects in April 2026