"Creating assets is only half the task; ensuring their functionality is the other." Examine this statement in light of the shift in focus under Jal Jeevan Mission 2.0.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →Jal Jeevan Mission (2019) promised a Functional Household Tap Connection delivering 55 lpcd to every rural home. Coverage has risen from 16.65% to nearly 16 crore households [3][1]. The word "functional", however, has proved harder to deliver than the pipe. JJM 2.0 recognises this and restructures the mission from infrastructure creation to service delivery [2].
Why assets alone are half the task
- The functionality gap: the 2022 national assessment found about 86% of connected households had working taps [4]. Roughly 1 in 7 "covered" homes still lacked reliable water.
- Missing O&M frameworks: 2026 CAG audits found States had not prepared O&M policies and had collected little of the community contributions due [5][6]. Unmaintained schemes become stranded capital.
- The skill deficit: villages lack technicians for leaks, valves and pumps, so small faults turn into long outages.
How JJM 2.0 shifts the focus
- Outcome-linked funding: the mission is extended to Dec 2028 with ₹8.69 lakh crore. Central funds depend on States meeting reform conditions [2].
- Community certification: Gram Panchayats certify "Har Ghar Jal" only once sustainable O&M arrangements are in place [2].
- Nal Jal Mitra: under a DDWS–DGT MoU, at least 1 lakh ITI/NSTI youth will get a 165-hour NSQF-aligned course with 45 hours of on-the-job training. The cost is about ₹111.93 crore [1]. This is a whole-of-government pairing of the water and skilling departments.
Gaps that remain
- Training, not wages: States engage the certified youth "under their own HR policies" [1]. Without user fees or Panchayat funds, no one may pay them.
- Unclear accountability: it is not settled whether the VWSC, the Gram Panchayat or the PHED employs the operator and answers for repairs [5].
- Wrong metric: "1 lakh certified" counts certificates, not working taps.
Building assets and keeping them working are therefore two equal halves of service delivery. JJM 2.0 rightly makes functionality the goal. To close the loop, States should notify O&M policies, Panchayats should levy modest water fees, and the next round of funding should be tied to how many certified youth are deployed and how functionality scores improve [4][6]. This would make the Eleventh Schedule's vision of Panchayat-run drinking water, and SDG 6, real.
Sources
- 1PIB: DDWS–DGT MoU on Nal Jal Mitra skilling programme under JJM 2.0 (Nov 2026)1 lakh target, 165 h/45 h OJT course, ₹111.93 crore, States' HR policies, ~16 crore coverage
- 2PIB, Ministry of Jal Shakti: Cabinet approves extension and restructuring of Jal Jeevan Mission (Mar 2026)Dec 2028 extension, ₹8.69 lakh crore, service-delivery focus, conditional funds, GP certification
- 3PIB Backgrounder on Jal Jeevan Mission (Oct 2024)FHTC, 55 lpcd, 16.65% baseline at launch
- 4DDWS: National Report of Functionality Assessment 2022~86% of households had working taps
- 5CAG Performance Audit on JJM (2026), Chapter VI: Post-operational managementO&M policy gaps; VWSC/PHED roles
- 6CAG Performance Audit on JJM (2026), Audit Snapshotrecommends an O&M policy and a mechanism for collecting community contributions