"Creating health infrastructure is necessary but not sufficient." Examine this with reference to the gap between approval and operation under PM-ABHIM.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
The Pradhan Mantri Ayushman Bharat Health Infrastructure Mission (PM-ABHIM) has an outlay of ₹64,180 crore for 2021-22 to 2025-26 [2] and has approved 19,983 infrastructure units [1]. In November 2026, the Union Health Secretary's review moved the focus from sanctioning units to making them functional [1]. That shift admits that buildings alone do not deliver care.
Why infrastructure is necessary
- Thin public capacity: India has only 0.79 public-sector beds per 1,000 people [3].
- Pandemic preparedness: COVID-19 exposed weak labs and surveillance. PM-ABHIM funds 744 district Integrated Public Health Labs and 2,151 Block Public Health Units [1].
- Last-mile access: It funds 11,001 AAM–Sub Health Centres, some at sites that had no building, and 5,456 Urban AAMs [1].
Why it is not sufficient: the approval–operation gap
- Poor fund absorption: In 2023-24 the budget estimate (BE) was ₹4,200 crore [4], but actual spending was only ₹2,230 crore [5], about 53%.
- Missing staff: The CAG found a 77–87% shortfall of specialists in CHCs under NRHM [6]. PM-ABHIM's targets count units, not doctors.
- Federal cost-shift: PM-ABHIM is a Centrally Sponsored Scheme [2], and health is a State subject (Entry 6, List II). So recurring salary and maintenance bills fall on States. Fiscally weak States may leave finished units idle.
- Under-funded system: Public health spending is 1.8% of GDP, against the National Health Policy 2017 target of 2.5% [7].
- Operational lag: Equipment, staff and day-to-day running arrangements trail construction [1].
Approval → Building → Equipment → Staff → Recurring funds → Functional unit
└── capex (Centre-led) ──┘ └──── revenue (State-borne) = bottleneck ────┘
Fig: Where approved units stall
Way forward
- Measure the right thing: Track staffed, working units, not approvals, and pool funds from different schemes for the same facility (convergence of investments) [1].
- Staff first: Create and fill posts before a unit opens.
- Running costs: In the scheme's next phase, the Centre should share running costs for the first few years and taper its support.
- Protect capital: Ring-fence building money through the Parliamentary Standing Committee's proposed Healthcare Capital Expenditure Fund [3].
- Targeted PPP: Use public-private partnerships for district diagnostics and equipment upkeep where paying demand exists.
Infrastructure is the skeleton of a health system; staff, recurring funds and governance keep it alive. Closing the approval–operation gap through cooperative federalism and assured running costs will turn PM-ABHIM's assets into working care. This advances Article 47 and SDG 3's goal of universal health coverage.
Sources
- 1PIB Press Release: Union Health Secretary's national workshop reviewing NHM and PM-ABHIM, Bengaluru (Nov 2026)19,983 approved units; shift to making units functional; IPHL, BPHU and AAM figures; equipment and operational gaps; convergence of investments
- 2PIB, Ministry of Health and Family Welfare: PM-ABHIM (Dec 2024)₹64,180 crore outlay for 2021-22 to 2025-26; Centrally Sponsored Scheme structure
- 3PRS Report Summary: Affordability and Accessibility of Healthcare in India (176th Report, Standing Committee on Health and Family Welfare, Aug 2026)0.79 public-sector beds per 1,000 people; Healthcare Capital Expenditure Fund
- 4PRS Demand for Grants 2023-24 Analysis: Health and Family WelfarePM-ABHIM 2023-24 BE of ₹4,200 crore
- 5PRS Demand for Grants 2025-26 Analysis: Health and Family WelfarePM-ABHIM 2023-24 actual spending of ₹2,230 crore
- 6CAG Report No. 25 of 2017, Chapter 5: Availability of Human Resources (Performance Audit of RCH under NRHM)77–87% specialist shortfall in CHCs
- 7PRS Demand for Grants 2026-27 Analysis: Healthpublic health spending of 1.8% of GDP against the 2.5% target