·PIB·15 marks·250–350 words

Critically evaluate the Greenfield Airports Policy, 2008 in expanding regional air connectivity. What bottlenecks persist in its implementation?

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. Achievements
  2. Limitations
  3. Bottlenecks that persist

The Greenfield Airports (GFA) Policy, 2008 sets a two-stage approval process for new airports built on undeveloped land. The Ministry of Civil Aviation (MoCA) first grants Site Clearance and then In-Principle Approval, and a Steering Committee chaired by the Secretary, Civil Aviation, monitors the clearances [1]. The policy has added airports to India's map. But approvals have been slow to turn into regular regional flights.

Achievements

  • Clear approval framework: by August 2023, 21 greenfield airports had in-principle approval and 12 were operational [1].
  • A way out of civil enclaves: a new airport can replace a civil terminal that is boxed in by a defence airfield. The Parliamentary Standing Committee endorsed this option [2]. The Doloo (Silchar) airport, approved by CCEA at Rs.2,014 crore and built by AAI, replaces such an enclave [4].
  • Regional development: Doloo links the Barak Valley's tea, agro-industry and tourism to national growth corridors. Its modular, green terminal can be expanded as traffic grows [4].

Limitations

  • Slow delivery: of 13 approved airports, four took 10 years and one took 20 years to start operating [2].
  • A runway does not guarantee flights: at Pakyong (Sikkim), poor visibility stopped flights twice. The airline flew only 4 of its 10 allotted UDAN routes [5].
  • No clear selection rule: the Committee asked for set criteria for choosing between a greenfield and a brownfield airport [2].

Bottlenecks that persist

  • Land and resettlement: MoCA depends on States to hand over land. Court cases over rehabilitation and resettlement (R&R) cause major delays [2].
  • Routes do not survive without subsidy: of 90 UDAN routes started in the North-East, only 38 still operate. 28 stopped once their three-year viability gap funding (VGF) ended [3].
  • Civil–defence friction: India has 31 civil enclaves. Air traffic controllers are overworked, flights are limited to defence "watch hours", and defence permissions are tied to lease rent [2].
  • Operating problems: low demand and shortages of aircraft [3].

The GFA Policy works well as an approval system but falls short as a connectivity tool. Its role largely ends once construction begins. It needs three additions: month-by-month tracking of land acquisition, the Modified UDAN's tapered VGF for up to five years [3], and joint MoCA–Defence plans for enclaves [2]. Together, these would turn new runways into lasting regional air links, in line with SDG 9 on resilient infrastructure.

Sources

  1. 1PIB, Ministry of Civil Aviation: Greenfield Airports Policy status – 21 approved, 12 operationalised (Aug 2023): the two-stage approval process, the Steering Committee, and the 21/12 status
  2. 2PRS Report Summary: Standing Committee on Transport, Tourism and Culture, "Development of Greenfield and Brownfield Airports and Issues pertaining to Civil Enclaves in Defence Airports" (July 2023): delays of 10 and 20 years, land and R&R litigation, 31 enclaves, watch hours and lease rent, the full-fledged airport option, greenfield vs brownfield criteria
  3. 3Lok Sabha Unstarred Question No. 703 (23 July 2026): Modified UDAN Scheme for North-Eastern States: 90/38/28 North-East route figures, reasons airlines left routes, tapered VGF for up to five years
  4. 4PIB: CCEA approves Greenfield Airport at Doloo, Silchar, Assam (25 Nov 2026): Rs.2,014 crore cost, AAI as builder, the civil enclave being replaced, Barak Valley economy, modular green terminal
  5. 5CAG Union Government (Commercial) Report No. 15 of 2023 – Pakyong airport observations: flights stopped twice by poor visibility, 4 of 10 routes flown