·PIB·15 marks·250–350 wordsGeographyPolityEconomy

Despite policy push, IWT's modal share in India remains low. Analyse the constraints and evaluate demand-side incentives such as Jalvahak.

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. Constraints on modal shift
  2. Evaluating Jalvahak

Cargo on National Waterways rose from 18 MMT (2013-14) to 218 MMT (2025-26) [1]. Yet inland water transport (IWT) still carries only about 2% of India's freight, against 48% in Vietnam and 49% in the Netherlands [2]. The gap is mainly on the supply side, so demand-side incentives can help only in part.

Constraints on modal shift

  • Declared ≠ navigable: only 23 of 111 notified waterways work; 63 are shelved for lack of money and staff [2].
  • Concentration: five waterways carry 80% of IWT cargo [2], so national growth hides idle routes.
  • Fairway reliability: braided, silt-heavy rivers like the Brahmaputra need dredging every year [1]. Shippers won't commit without year-round depth, and the government hesitates to pay without cargo. This is a chicken-and-egg trap.
  • Weak hinterland connectivity: poor road and rail links to jetties force double handling, which wipes out the cost advantage [2].
  • High vessel and equipment costs, plus too few loading and unloading terminals [2].
  • Ecological limits: dredging on NW-1 disturbed the Gangetic dolphin [2].

Evaluating Jalvahak

Strengths

  • It reimburses up to 35% of operating costs for cargo moved more than 300 km on NW-1, NW-2 and NW-16 [3]. This directly meets the Standing Committee's call for shipper incentives [2].
  • It was launched alongside fixed, scheduled cargo services from Haldia, which makes trips more predictable [3].
  • Early signs are good: a record 145.5 MMT in FY25 [4], and the first international cargo from Bogibeel (540 MT methanol) left for Dhaka in October 2026 [1].

Limitations

  • An operating subsidy does not dredge channels, build last-mile links or lower vessel prices.
  • It is small (₹95.4 crore) and runs for a fixed three years [3]. If the subsidy is the only advantage, cargo may go back to trucks when it ends.
  • Early users are PSUs such as APCL [1]. Private shippers have not yet committed.

Verdict: Jalvahak is a needed spark but cannot fix the problem alone.

Overall, IWT's low share comes from gaps in infrastructure and reliability that a demand subsidy cannot cure on its own. Jalvahak should be combined with the Standing Committee's advice [2]: plan rail, road and port links when a waterway is designed, build terminal capacity, and carry out environmental assessment before dredging. Effort should go to a few viable corridors, not paper waterways. With this, the 5%-by-2030 target [2] is within reach, and it would advance SDG 9 (infrastructure) and SDG 13 (climate action).

Sources

  1. 1Dibrugarh Sends First International Cargo from Bogibeel to Bangladesh Since Independence (PIB, 05 Oct 2026)18→218 MMT growth, Brahmaputra siltation, 540 MT APCL methanol shipment
  2. 2PRS Legislative Research: Standing Committee Report Summary on Development and Expansion of Existing and New National Inland Waterways (2023)2% modal share, 111/23/63 waterways, 80% concentration, barriers, dolphin impact, recommendations, 5% target
  3. 3Govt Unveils 'Jalvahak' To Boost Inland Waterways (PIB, Dec 2024)35% reimbursement, >300 km, NW-1/2/16, ₹95.4 crore, scheduled services, three-year duration
  4. 4Cargo traffic on National Waterways hits record high of 145.5 million tonnes in FY 2024-25 (PIB)FY25 record cargo
Practice
6 questions on this item
Check the answer for each question, or reveal all at once.
Practice MCQs →

More from this note

More on Geography