·PIB·15 marks·250–350 words

Discuss how India's 5G rollout and the push to make telecom equipment in India can help bridge the digital divide. What challenges remain?

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. 5G rollout as a bridge
  2. Make in India in telecom
  3. Challenges that remain

The digital divide is the gap between people who can use digital technology and people who cannot. A decade ago it made modern connectivity a privilege of those who could afford it [1]. 5G was launched from the India Mobile Congress stage in 2022 and now reaches every district [1]. Together with domestic telecom manufacturing, it is narrowing the gap, but the last mile is still unfinished.

5G rollout as a bridge

  • Scale and speed: India has more than 5.5 lakh 5G base stations, and mobile internet is about 10× faster than in 2022 [1].
  • Governance on the phone: Hundreds of services are now on mobile phones. DBT has sent about ₹50 lakh crore directly to beneficiaries [1].
  • Education: DIKSHA logged over 500 crore learning sessions up to July 2022, reaching children in remote villages [1].
  • Less travel: Citizens no longer need to visit distant banks, hospitals or block offices for routine services [1].

Make in India in telecom

  • Affordability: Telecom reforms and making phones and network hardware in India made data and devices cheaper [1]. This lowers the cost of getting online for poor households.
  • Industrial linkage: The IMC agenda of "Invest, Innovate, Make in India" ties connectivity to jobs and domestic capacity [1].
  • Global voice: India hosted the GSMA Board meeting in 2026, which signals a growing role in telecom governance [1].

Challenges that remain

  • District is not village: BharatNet's fibre was "service ready" in 2.19 lakh Gram Panchayats (96.70%), but only against a revised scope of 2.26 lakh. Work ran 2–6 years late, partly because Right of Way clearances were slow [2].
  • Reliability: Fibre faults caused about 48% of network downtime, and the average repair took 17 days [2].
  • Device gap: Only 85.5% of households own a smartphone, so roughly one in seven are left out of app-based services [3].
  • Exclusion by design: MGNREGA wages were delayed by inactive Aadhaar and frozen bank accounts [4]. When the technology fails, the payment fails too.

5G and domestic manufacturing have largely solved the supply side of the divide: coverage and cost. The way forward is to:

  • judge BharatNet by uptime and actual use, not just cable laid;
  • speed up Right of Way clearances with the States;
  • keep non-digital fallbacks for payments, as the Standing Committee urged [4].

Only then will connectivity serve Antyodaya and SDG 9.c, the goal of universal, affordable internet access.

Sources

  1. 1PIB – Text of PM's address at the inauguration of the 10th edition of the India Mobile Congress (8 Oct 2026)5G in every district, 5.5 lakh+ base stations, 10× speed, DBT ₹50 lakh crore, DIKSHA, cheaper devices through domestic manufacturing, GSMA Board
  2. 2CAG Audit Report No. 19 of 2026 – Performance Audit of BharatNetservice-ready share against the revised scope, 2–6 year delays, Right of Way, fibre-fault downtime, 17-day repair time
  3. 3MoSPI/NSO – Comprehensive Modular Survey: Telecom, 2025 (via PIB)85.5% of households own a smartphone
  4. 4PRS – Report Summary: Critical Evaluation of MGNREGA (Standing Committee on Rural Development and Panchayati Raj)wage delays from inactive Aadhaar and frozen bank accounts; fallback recommendation

More from this note