Under DBFOT (Design, Build, Finance, Operate and Transfer), a private concessionaire builds and runs a port terminal for a fixed period and then hands it back. The Government recently approved Kamarajar Port's second container terminal under this model: 2 million TEUs, ₹4,288.26 crore and a 40-year concession [1]. The model suits port terminals, but only if risk is allocated with discipline.

Merits: why DBFOT fits ports

  • Fiscal leverage: private capital pays for the terminal. KPL spends only about ₹450 crore, and only on dredging [1].
  • Phased build: Phase I operates from month 25 and the full terminal from month 49. This brings in revenue early and limits idle capacity [1].
  • Commercial flexibility: under the Model Concession Agreement 2021, operators set tariffs by market conditions after TAMP's tariff role ended [3].
  • Public ownership retained: the assets return to the port after the concession. This matches Maritime India Vision 2030's push for private participation [2].

Limitations: the record so far

  • Delays: the CAG found pre-contract delays in 35 of 39 port PPPs. Delays on the port's side, such as late site handover, ran up to 455 days [4].
  • Demand risk: Cochin's ICTT ran at only about 35% of capacity [4]. KPL used only 56.66% of its port-wide capacity in 2024–25. Chennai Port shares its hinterland and handles 13.43% of major-port container traffic, against KPL's 5.03% [5].
  • Weak oversight: the CAG could not conclude that service was better at PPP berths. JNPT lost ₹54.72 crore by giving a neighbouring berth to the same operator at a lower revenue share [4].
  • No price regulator: only competition now keeps tariffs in check [3].

Allocating risk: whoever controls a risk should bear it

  • Port authority: handing over land and the backup area, capital dredging, clearances, appointing the Independent Engineer on time [4], and road–rail links coordinated with the states.
  • Concessionaire: design, construction, financing, operations, tariffs and efficiency.
  • Shared demand risk: the royalty is paid per TEU and indexed to WPI, so the port's revenue already depends on traffic [3]. Phase II should open only when Phase I is close to full.
  • Accountability: each terminal should publish yearly data on ship waiting time, handling speed and capacity use. Revenue terms for neighbouring berths should be checked closely.

Overall, DBFOT suits port terminals, which earn their own revenue. Its results depend on the port authority meeting its own obligations. If each risk goes to the party best placed to manage it, expansion follows traffic, and performance is made public, DBFOT can deliver the efficient and accountable port growth that Maritime India Vision 2030 envisions [2].

Sources

  1. 1Govt approves second container terminal at Kamarajar Port, PIB, 25 Nov 20262 million TEU capacity, ₹4,288.26 crore cost, 40-year concession, ₹450 crore KPL dredging, month-25/49 phasing
  2. 2Maritime India Vision 2030 Report, Ministry of Ports, Shipping and Waterwaysprivate participation and port-capacity priorities
  3. 3New Model Concession Agreement 2021 for PPP Projects at Major Ports, PIBmarket-set tariffs, end of TAMP's tariff role, per-TEU royalty indexed to WPI
  4. 4CAG Report No. 49 of 2015: Performance Audit of PPP Projects in Major Portsdelays in 35 of 39 projects, handover delays up to 455 days, Cochin ICTT at 35% capacity, unproven service gains, JNPT ₹54.72 crore loss
  5. 5Update on Indian Port Sector up to 31.03.2025, Ministry of Ports, Shipping and WaterwaysKPL port-wide utilisation 56.66%; container shares of Chennai (13.43%) and KPL (5.03%)
Practice
6 questions on this item
Check the answer for each question, or reveal all at once.
Practice MCQs →

More from this note

More on Geography