·PIB·15 marks·250–350 words

"Hydropower cooperation is the cornerstone of a mutually beneficial India–Nepal partnership." Examine with reference to recent initiatives and implementation challenges.

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. Mutual benefits
  2. Recent initiatives
  3. Implementation challenges

During Nepal PM Balendra Shah's November 2026 visit, India's Prime Minister called Nepal's clean-energy potential the core of Nepal's prosperity [1]. In principle, hydropower is the cornerstone of the partnership. In practice, delivery has lagged behind ambition.

Mutual benefits

  • Nepal: India gives it an assured market and export earnings. Nepal exported about 1,100 MW to India last year [2].
  • India: Nepal supplies low-carbon power for India's energy transition, from a friendly neighbour.
  • Region: Nepal has sent power to Bangladesh through the Indian grid, so India also acts as a route to a third market [2].

Recent initiatives

  • Arun-3 (900 MW): built by Indian PSU SJVN, it will be Nepal's largest project. India has promised to finish it on time [1][2].
  • Lower Arun (~670 MW): foundation laid during the 2026 visit [1].
  • Grid links: Muzaffarpur–Dhalkebar is operational and Gorakhpur–Butwal is at an advanced stage. Joint ventures have been signed for Inaruwa–Purnea and Dododhara–Bareilly [2].
  • Frameworks: a 10,000 MW export target and the 2022 Joint Vision on Power Sector Cooperation [2].

Implementation challenges

  • Delivery gap: actual exports of about 1,100 MW are a small fraction of the 10,000 MW target [2].
  • Seasonal mismatch: run-of-river plants produce most in the monsoon, but Nepal's demand peaks in winter. So Nepal sells in summer and buys from India in winter [5].
  • Stalled storage project: the Mahakali Treaty (1996) provides for Pancheshwar to be built on a jointly prepared DPR [4]. The DPR was still only a 'draft final' in 2018-19 [6].
  • Regulatory asymmetry: India's 2018 cross-border electricity rules restrict buying power from projects funded by third countries [5]. Nepal sees this as limiting its choice of financiers.
  • Weak monitoring: the Standing Committee on External Affairs (2023) called for fixed deadlines and stronger Joint Project Monitoring Committees [3].
  • Fear of dependence: India takes over 80% of Nepal's goods exports [2]. Because an Indian PSU builds the flagship projects, any delay becomes a political issue.
  • Ecological risk: large projects in the seismically active, fragile Himalaya need careful environmental scrutiny.

Hydropower does bind the two economies' interests, but it is still more promise than delivered power. Four steps could turn the 10,000 MW target into real supply:

  • give priority to storage projects such as Pancheshwar;
  • publish stable trade rules and review them jointly with Nepal;
  • set time-bound timetables for each project;
  • strengthen joint monitoring.

That would advance SDG 7 and the shared vision of "Viksit Bharat" and "Samunnat Nepal" [1].

Sources

  1. 1Press statement by PM during Joint Press Statement with PM of Nepal, PIB (23 Nov 2026)clean energy as core of Nepal's prosperity; Arun-3 on-time pledge; Lower Arun foundation; Viksit Bharat–Samunnat Nepal vision
  2. 2India–Nepal Bilateral Relations brief, Ministry of External Affairs (July 2026)~1,100 MW exports; 10,000 MW target; Arun-3/Lower Arun by SJVN; transmission lines; Bangladesh power trade; 2022 Joint Vision; trade-dependence figures
  3. 3India's Neighbourhood First Policy – Standing Committee on External Affairs, Report Summary (PRS, 2023)fixed deadlines and stronger Joint Project Monitoring Committees
  4. 4Mahakali Treaty, 1996 (treaty text)Pancheshwar to be built on a jointly prepared DPR
  5. 5Regional Electricity Trade for Hydropower, World Bank (2021)run-of-river seasonal mismatch; India's 2018 third-country funding restriction
  6. 6Annual Report 2018-19, Ministry of Water Resources, RD & GRPancheshwar DPR still at 'draft final' stage