·The Hindu·15 marks·250–350 wordsGeographyEnvironment

Hydropower development in India's northeastern border states involves a trade-off between strategic infrastructure needs and ecological conservation. Discuss with examples.

In this answer
  1. Strategic and developmental case
  2. Ecological and social costs
  3. Governance and assessment gaps

The eastern Himalaya holds India's largest untapped hydropower reserve — in Arunachal Pradesh alone, twelve stalled projects of about 11,517 MW were transferred to central power PSUs for revival [1]. Harnessing this serves energy and frontier security, but the same free-flowing rivers sustain irreplaceable biodiversity, making the trade-off sharp rather than notional.

Strategic and developmental case

  • Energy security: storage projects like the 2,880 MW Dibang Multipurpose Project supply peaking power, flood moderation and clean capacity toward India's non-fossil targets [2].
  • Border consolidation: dams in frontier districts such as Anjaw and Dibang Valley bring roads, transmission corridors and settled populations to a sensitive Sino-Indian boundary, and assert lower-riparian use against upstream damming on the Yarlung Tsangpo.
  • Fiscal stake: free power share and royalties are among the few revenue sources for resource-scarce hill states.

Ecological and social costs

  • Loss of specialist habitat: the 1,200 MW Kalai-II project on the Lohit (Anjaw), granted in-principle forest clearance, affects the last Indian refuge of the white-bellied heron — Critically Endangered with fewer than 60 birds globally [3] and Schedule I protected under the Wild Life (Protection) Act, 1972 [4]. It feeds only in shallow, clear rapids that reservoirs and altered sediment flows destroy.
  • Cumulative basin effects: appraisal proceeds project-by-project, though a basin like the Lohit functions as one connected habitat; seismic Zone-V siting adds downstream risk, as protests over Subansiri Lower showed.

Governance and assessment gaps

  • Impact assessments that omit resident endangered species weaken the credibility of forest clearance under the Forest (Conservation) framework [5].
  • Compensatory afforestation for this diversion was approved in Madhya Pradesh; funds under the CAMPA architecture [6] can replace tree cover but not a site-specific riverine ecosystem.

Development and conservation here are sequencing problems, not opposites. Basin-level cumulative impact assessment, in-situ compensatory afforestation, and prioritising low-impact run-of-river sites over ecologically critical stretches can secure both energy and the border — honouring Article 48A and SDG 15 alongside SDG 7.

Sources

  1. 1PIB — 12 stalled hydro power projects of Arunachal Pradesh (11,517 MW) handed to hydro PSUsscale of stalled/revived hydropower capacity
  2. 2PIB — Foundation stone for 2,880 MW Dibang Multipurpose Hydroelectric Projectflagship storage project example
  3. 3IUCN Red List — *Ardea insignis* (White-bellied Heron)Critically Endangered status, global population under 60
  4. 4The Wild Life (Protection) Act, 1972, India CodeSchedule I legal protection
  5. 5PARIVESH — Forest Clearance, Acts, Rules and Guidelines (MoEFCC)forest clearance appraisal framework
  6. 6National CAMPA, MoEFCC — Compensatory Afforestationcompensatory afforestation fund mechanism