·The Hindu·15 marks·250–350 words

Linking civic utilities and bank finance to completion certificates is a regulatory innovation. Discuss its potential and its limits.

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. Potential
  2. Limits

In Rajendra Kumar Barjatya v. U.P. Avas Evam Vikas Parishad (2024), the Supreme Court directed that water, electricity and sewage connections, and bank loans against a building, be given only after a completion/occupancy certificate (CC/OC) is verified [1]. This moves enforcement from slow demolitions to the points where a building gets money and services. That holds great promise, but it is only as strong as the certificate itself.

Potential

  • Cuts off money for illegal buildings: without loans or utilities, unauthorised floors become hard to fund, sell or live in [1].
  • Acts before, not after: the Court called post-construction inspection "a sham" that turns violations into a fait accompli [2]. Checking at the gate stops a violation before anyone moves in.
  • Protects buyers: bank checks give homebuyers built-in due diligence. Fewer good-faith buyers end up facing demolition [3].
  • Adds more watchdogs: lenders and utilities become extra checkpoints. Departmental action against officers who issue wrong CCs and on-site display of the approved plan add accountability [1].
  • Upholds rule of law: it fits with Kaniz Ahmed (2025), which ruled out "judicial regularisation" because it breeds impunity [3].

Limits

  • The issuer may be compromised: the same municipal bodies accused of "active connivance" issue the CCs [2]. CAG found Faridabad's corporation gave an OC to a ₹182.46 crore building on protected notified land [5].
  • No follow-up: in Madhya Pradesh, 33,016 permissions (2018–21) were never checked for CCs [4].
  • Weak deterrent: departmental action is internal discipline, and it is rarely enforced.
  • Existing buildings left out: the rule protects future buyers. It does little for people already living in such buildings, who may turn to informal connections.
  • Political override: State regularisation schemes timed "before an impending election" weaken the incentive to comply [2].
  • Uneven capacity: building control is a ULB function under the Twelfth Schedule (74th Amendment). That is why the Court has brought in the capital-city corporations of all States and UTs [6] and asked them for suggestions [2].

The linkage is a smart preventive tool, but it cannot replace honest certification. It needs public digital permit registers, inspection at each stage of construction, outside audits of CCs and a legal bar on repeat regularisation. Together these would turn a court directive into lasting urban governance, in line with the 74th Amendment's vision and SDG 11.

Sources

  1. 1Supreme Court of India: Judgment in *Rajendra Kumar Barjatya v. U.P. Avas Evam Vikas Parishad* (17 Dec 2024): utilities and loans only after a CC/OC; departmental action against officers; approved plan displayed on site
  2. 2The Hindu: Court flags 'connivance' of civic authorities in flagrant violation of building bylaws (24 Nov 2026): "active connivance", pre-election regularisation, inspections "a sham" and a fait accompli, suggestions sought from States and UTs
  3. 3Supreme Court of India: Judgment in *Kaniz Ahmed v. Sabuddin* (30 Apr 2025): no judicial regularisation; culture of impunity
  4. 4CAG Report No. 5 of 2025: Town and Country Planning, Government of Madhya Pradesh069985b0813fdf7.38091434.pdf): 33,016 permissions never checked for CCs
  5. 5CAG Report No. 7 of 2022: Compliance Audit, Government of Haryana: Faridabad OC for a ₹182.46 crore building on notified land
  6. 6Supreme Court of India: Order in *Loganathan v. State of Tamil Nadu* (25 Mar 2026): municipal bodies of all State and UT capitals impleaded