Long-duration space missions face technical setbacks and schedule slippage. Explain this with recent examples and suggest ways to reduce the risk.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
Long-duration space missions spend years in transit. Their success then depends on one-time manoeuvres that cannot be rehearsed on the real spacecraft. The ESA–JAXA BepiColombo mission launched in 2018 and entered Mercury orbit only in November 2026, after an eight-year cruise [1]. Such risks are built into these missions, but they can be managed.
Recent examples of setbacks and slippage
- Software glitch at the critical moment: BepiColombo's orbit-insertion thruster burn was shorter than planned because of a software issue. The spacecraft is safe and the European Space Operations Centre (ESOC) is investigating [1].
- Schedule slippage: orbit insertion was once planned for 5 December 2025 [2] but happened on 21 November 2026. Routine science starts only in April 2027 [1].
- Descent failure: Chandrayaan-2's lander had a lapse about 13 minutes into its descent in September 2019 [3].
Why risk builds up over long missions
- Orbital physics: Mercury is hard to stop at. A craft falling towards the Sun gains speed, so long, indirect routes are needed to shed that speed [1].
- Ageing hardware: systems designed before 2018 must work flawlessly almost a decade later.
- Untestable one-time events: orbit insertion, separation and landing happen only once, at the destination.
- Coupled risk: JAXA's Mio rides on the shared stack until separation on 9–10 December 2026 [1][2]. A fault before then hits both partners.
Ways to reduce the risk
- Failure-based redesign: Chandrayaan-3 made changes to strengthen the lander and checked them through exhaustive ground tests and simulations [3]. These built on lessons from Chandrayaan-2 [4].
- Software assurance: independent verification, simulated critical burns and in-flight software patching.
- Engineering margins: fuel reserves and backup manoeuvre windows to make up for shortfalls.
- Date windows, not single dates: a slip then does not read as a failure.
- Clear partnership design: split the work by module, as with ESA's MPO and JAXA's Mio [2], and agree in advance who leads a failure review.
BepiColombo's safe arrival despite its glitch [1] and Chandrayaan-3's success after Chandrayaan-2 [4] show that robust design, margins and open failure reviews turn setbacks into lessons. Building these practices in will make India's growing interplanetary programme reliable and cost-effective, in line with SDG-9's focus on innovation.
Sources
- 1The Hindu (Reuters news report): "BepiColombo: Mercury in view", 25 Nov 20262018 launch and 8-year cruise; orbit entry on 21 Nov 2026; software-related short thruster burn; ESOC investigation; separation on 9–10 Dec 2026; science from April 2027; orbital-physics difficulty *(the exact article page could not be verified, so the link goes to the site's home page)*
- 2NASA Science: BepiColombo mission pageearlier planned orbit insertion of 5 Dec 2025; two orbiters (ESA's MPO and JAXA's Mio) travelling as one stack
- 3PIB: Dr Jitendra Singh on the upcoming Chandrayaan-3 launch (Ministry of Science & Technology)Chandrayaan-2 lapse about 13 minutes into descent; Chandrayaan-3 lander changes checked through exhaustive ground tests and simulations
- 4ISRO: "The making of Chandrayaan-3: collaborative effort under the 'ISRO culture'"Chandrayaan-3 lander built on lessons from Chandrayaan-2's failed landing