Multimodal integration is key to reducing project cost overruns. Discuss with reference to the movement of heavy industrial equipment.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
Steam generators, turbines and transformers move as Over-Dimensional Cargo (ODC). In 1976, BHEL Tiruchi's 60-tonne steam generator for the Madras Atomic Power project was too wide for rail. It then waited 13 days at the factory gate for highway clearance [1]. Bottlenecks like this, caused by relying on one mode, show why linking road, rail, waterways and ports is central to keeping project costs in check.
How single-mode dependence inflates project cost
- Rail clearance limits: a load is classed as ODC if it exceeds Standard Moving Dimensions at even one point on the route. Electrified sections also need extra coordination to protect the overhead power lines [2].
- Unknown bridge capacity: in 1976 the Coleroon bridge was load-tested only on the day of the move. The unfinished Thozhudur bridge forced a detour via Perambalur [1].
- Permit delays: MoRTH brought in online, real-time ODC/OWC permits only in 2020 [3].
- Rigid ports: major ports handle ODC only in daylight [4], and port infrastructure has been built mainly for containers [5].
How multimodal integration reduces overruns
- Shared route planning: the PM GatiShakti National Master Plan puts road, rail, port and waterway projects on one map. This lets agencies check routes at the design stage instead of improvising diversions [6].
- Waterways for heavy cargo: NW-1 (Ganga) has carried power-plant ODC such as steam turbine and generator parts [7]. Cargo on National Waterways reached 145.84 MMT in FY 2024-25, and a scheme pays back up to 35% of the operating cost of a waterway trip [8].
- Lower system cost: the first official estimate puts India's logistics cost at 7.97% of GDP [9]. That national average, however, hides the very high cost of one-off heavy consignments.
Limitations
- MoRTH's online permits cover only National Highways and single-unit loads on hydraulic trailers [3]. State roads still have no advance bridge-load data.
- The last mile still depends on roads, and each transshipment (shifting cargo between modes) adds handling risk and cost.
Multimodal integration turns ODC movement into a planned part of the project rather than something worked out after the equipment is built. Three steps would help:
- states carry out bridge-load surveys linked to the national online permit portal
- ports allow ODC handling at night under proper safety rules
- route clearance becomes a required part of the Detailed Project Report (DPR) under GatiShakti
Together, these support SDG 9 (resilient infrastructure) and indigenous capital-goods manufacturing.
Sources
- 1Too big a load for rail and road, *The Hindu*, "50 years ago", 29 Oct 20261976 move of BHEL's steam generator; too wide for rail; 13-day wait; Coleroon/Thozhudur bridges; Perambalur detour
- 2Indian Railways (CAMTECH), Safety Pamphlet on movement of ODC in electrified sectionStandard Moving Dimensions; coordination for overhead power lines
- 3MoRTH Circular dated 10.06.2020 on ODC/OWC movementonline real-time permits on NHs; single-unit loads on Modular Hydraulic Trailers
- 4Ministry of Shipping, Dwell Time project reportODC handled only in daylight at major ports
- 5NITI Aayog, *Impact of Non-Major Ports on Shipping: Potential and Way Forward* (2025)port infrastructure built mainly for containers
- 6PIB, "PM GatiShakti National Master Plan can help lower our logistics cost to 7-8% of GDP"shared multimodal planning map
- 7Inland Waterways Authority of India, Waterwayssteam turbine and generator ODC moved on NW-1
- 8PIB, *A Ride through the Inland Waterways of India* (April 2026)145.84 MMT cargo in FY 2024-25; up to 35% of operating cost paid back
- 9PIB, *From Growth Engine to Global Edge: Supercharging India's Logistics* (Nov 2025)logistics cost at 7.97% of GDP, the first official estimate