PM GatiShakti marks a shift from siloed to integrated infrastructure planning. Assess its achievements in five years and the remaining institutional gaps.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
PM GatiShakti National Master Plan (PMGS-NMP) was launched on 13 October 2021. It put the route-fixing that each Ministry used to do alone onto one shared GIS platform. That platform covers 58 Central Ministries/Departments and all 36 States/UTs [1]. After five years, it has largely solved the information problem in infrastructure planning but not the enforcement problem.
Achievements
- One common map: the platform holds 23,493+ geospatial data layers. Bharatmala, Sagarmala, UDAN and inland waterways now sit on it together [1].
- Screening before sanction: a three-tier structure checks projects before they are approved. It has the EGoS (chaired by the Cabinet Secretary), the Network Planning Group and a Technical Support Unit. The NPG has evaluated 396 projects worth about ₹18.66 lakh crore [1].
- Open data: PM GatiShakti Public offers 230 datasets for site suitability, alignment planning and compliance checks [1].
- Cooperative federalism: 26 States/UTs had notified State Logistics Policies by 2024 [2].
- Capacity building: Gati Shakti Vishwavidyalaya has trained 2.4 lakh+ officers [1].
- Reliable baseline: the DPIIT–NCAER study puts logistics cost at 7.97% of GDP for 2023–24. This replaces older unofficial estimates of 13–14% [3].
Remaining institutional gaps
- Advisory, not binding: EGoS and NPG are committees of officials. Only 198 of the 396 evaluated projects are under implementation [1].
- Land and clearances: land is a State subject under the Seventh Schedule. The platform cannot acquire land under the RFCTLARR Act, 2013, and it cannot grant forest clearances.
- Uneven State uptake: some State policies were still drafts in 2025. Gaps in regulatory harmonisation and weak digital skills among small operators remain [4].
- No outcome data: no public figures show the time or cost saved per project. Smaller firms still pay much more for logistics [3].
- Multimodality incomplete: NITI Aayog says a seamless end-to-end network is still some way off [5].
- Split authority: a separate Integrated Transport & Logistics Authority (ITLA) was needed for 10+ year planning and for appraising projects of ₹500 crore or more. This shows the limits of the NMP [1].
PM GatiShakti has given India one shared map and a check before sanction, which is a real break from siloed planning. The next steps are:
- set up ITLA with data-use rules aligned to the DPDP Act, 2023;
- repeat the logistics-cost study every year, broken down by State and firm size;
- publish planned versus actual time and cost for sanctioned projects;
- train State revenue and forest officials.
Turning coordination into accountable delivery would anchor the National Logistics Policy's goal of reaching the top 25 of the Logistics Performance Index by 2030 [6].
Sources
- 1Five Years of PM GatiShakti: Transforming India's Infrastructure Planning (PIB, 12 Oct 2026)launch, coverage, data layers, three-tier structure, NPG pipeline, open datasets, GSV training, ITLA
- 2PM Gati Shakti: Transforming India's Infrastructure and Connectivity (PIB document, Oct 2024)26 States/UTs with State Logistics Policies
- 3Shri Piyush Goyal launches report on Assessment of Logistics Cost in India (PIB)7.97% of GDP; higher burden on smaller firms
- 4India Marks Three Years of National Logistics Policy (PIB)draft State policies; harmonisation and digital-skill gaps
- 5Speeding Up with Gati Shakti (NITI Aayog)seamless multimodal network still some way off
- 6PM GatiShakti NMP and NLP together will greatly help both businesses and people (PIB)NLP target of top 25 in the Logistics Performance Index by 2030
Practice