Tunnelling in the young fold mountains of the Himalaya poses unique engineering and ecological challenges. Discuss with reference to the Rishikesh–Karnaprayag Rail Project.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →The Himalaya are young fold mountains. Their rock is fractured and they are still tectonically active. The 125 km Rishikesh–Karnaprayag line runs close to the Main Central Thrust (MCT) [2] and needs about 213 km of tunnelling [3]. The breakthrough of the 6.59 km Tunnel-14 on 27 November 2026 shows both the difficulty and the progress [1].
Engineering challenges
- Seismic, heterogeneous rock: Because the alignment lies near the highly active MCT, tunnels must be designed for both earthquakes and weak rock [2].
- Loose soil under homes: At Sumerpur, a 110 m triple-track stretch had only 20–30 m of cover. It needed pre-excavation support and multi-drifting [1].
- Unstable portals: Ground settled at Marora. The slope needed 30–35 m micropiles, 15–20 m rock bolts and grouting before the main drive could begin in March 2024 [1].
- Technology limits: Indian Railways used a TBM (tunnel boring machine) in Himalayan geology for the first time to dig the 14.8 km T-8 tunnel [3].
- Worker safety: The 4.7 km drive needed mechanical ventilation throughout [1]. The Silkyara collapse in 2023 was traced to a weak temporary structure [5]. This line has 12 escape tunnels of about 98 km [2].
Ecological and social challenges
- Subsidence risk: In 2023 the NCMC ordered evacuation of parts of Joshimath in Chamoli district, which the alignment also enters [4].
- Vibration: Blasting was limited to daytime, and some stretches were dug mechanically to protect settlements [1].
- Displacement: Land and homes at Marora had to be acquired before digging could start [1].
- Counterpoint: Road cuts weaken slopes. On NH-107 alone, landslide and subsidence repairs are under way at 17 locations [6]. Tunnels avoid exposed slope faces.
Way forward
- Publish ground-settlement monitoring for the villages above the tunnels.
- Have an independent multi-institution panel, on the NDMA model, review the tunnels before the line opens [4].
- Treat a breakthrough as a milestone, not completion, because lining and systems work still remain [1].
The Rishikesh–Karnaprayag project shows that methods suited to each site, from multi-drifting to TBMs, can overcome Himalayan geology. Tunnelling is the more resilient choice in this terrain. It remains defensible only if monitoring is transparent and communities are protected. That would match the Sendai Framework and SDG 9's call for resilient infrastructure.
Sources
- 1PIB: Breakthrough Achieved in 6.59 km Long Tunnel-14 of Rishikesh-Karnaprayag Rail Project (Nov 2026)Tunnel-14 length and date, multi-drifting, micropiles and rock bolts, Marora settlement and acquisition, ventilation, daytime blasting, breakthrough ≠ completion
- 2PIB: Rishikesh-Karnaprayag new rail line (125 km), Lok Sabha reply125 km line, MCT seismicity, 12 escape tunnels (~98 km)
- 3PIB: India's Tunnels: Engineering Marvels Beneath the Surface (14 Jan 2026)213 km of tunnelling, first TBM in Himalayan geology, T-8 (14.8 km)
- 4PIB: Meeting of NCMC to review situation in Joshimath, Chamoli (10 Jan 2023)Joshimath evacuation, multi-institution expert team
- 5PIB: Stability and Progress of Infrastructure (Silkyara expert committee status)Silkyara collapse traced to a weak temporary structure
- 6New India Samachar (PIB), Vol. 6, Issue 12, Dec 16–31, 2025NH-107 landslide and subsidence repairs at 17 locations