·The Hindu

Building bridges

In this note
  1. At a Glance
  2. Why in the News
  3. Background & Evolution
  4. Core Static Facts
  5. Multi-Dimensional Analysis
  6. Recent Developments (last 12–18 months)
  7. Prelims Hooks
  8. Mains Relevance
  9. Related Topics to Study Next
  10. Common Errors / Trap Areas
Practice
5 questions on this article
Check the answer for each question, or reveal all at once.
Practice MCQs →

1. At a Glance

  • India's solar installed capacity has nearly doubled from ~15% of total installed capacity (2022) to ~28% (early 2026), yet solar's share of actual generation remains disproportionately low due to absence of large-scale battery storage. [1]
  • On India's record peak-demand day (April 25, 2026 — 256.1 GW), solar met 21.5% of the afternoon load but only 0.1% of evening demand, exposing the sunset gap. [1]
  • Battery Energy Storage Systems (BESS) are the critical bridge between intermittent solar generation and round-the-clock grid reliability — the central policy challenge of India's energy transition. [2]
  • UPSC relevance: GS-III (Energy, Infrastructure, Environment), national energy security, climate commitments (NDC/net-zero 2070).

2. Why in the News

  • April 25, 2026: India set a peak electricity demand record of 256.1 GW; solar supplied 21.5% of the afternoon load — an all-time high — yet covered only 10.8% of the full-day requirement and 0.1% of evening demand. [1]
  • 2025 curtailment data: India wasted 2.3 TWh of solar generation (May–December 2025), equivalent to 18% of average monthly solar output; 0.9 TWh was curtailed in October 2025 alone due to insufficient battery storage, imposing costs on the public exchequer for power never delivered. [1]
  • Government's second VGF Scheme for BESS (30 GWh, ₹5,400 crore) approved in June 2025 signals urgency. [3]

3. Background & Evolution

Year Milestone
2019 NITI Aayog publishes Energy Storage System Roadmap for India: 2019–2032 — first comprehensive ESS policy blueprint [4]
June 2021 PLI Scheme for Advanced Chemistry Cell (ACC) battery manufacturing approved (₹18,100 crore, 50 GWh capacity target) [5]
2022 Solar = ~15% of installed electric capacity; solar's share of generation on peak-demand day ≈ 5.6% [1]
March 2024 Cabinet approves VGF Scheme-I for BESS — ₹3,760 crore for 13,220 MWh at ₹27 lakh/MWh VGF [6]
February 2025 CEA advisory on co-location of ESS with solar projects: ≥10% of installed solar capacity for ≥2 hours [2]
June 2025 VGF Scheme-II approved — 30 GWh, ₹5,400 crore from Power System Development Fund (PSDF) at ₹18 lakh/MWh [3]
September 2025 CERC allows separate grid connectivity during non-solar hours, enabling storage-based shifting to evening/night [2]
Early 2026 Solar = ~28% of installed capacity; total two VGF schemes target ~43 GWh combined BESS [3]

4. Core Static Facts

Definitions & Classifications

  • BESS (Battery Energy Storage System): Grid-connected battery arrays that store surplus electricity for dispatch during deficit periods (evening/night/cloudy days).
  • Curtailment: Deliberate throttling of renewable generation to prevent grid destabilisation when storage/transmission cannot absorb surplus.
  • Energy Storage Obligation (ESO): Mandatory percentage of electricity that DISCOMs must procure from storage-backed sources; rises from 1% (FY 2023–24) to 4% (FY 2029–30) at +0.5%/year. [2]
  • Pumped Storage Plants (PSP): Hydro-based mechanical storage; complements BESS in long-duration storage.

Implementing Bodies

  • Ministry of New and Renewable Energy (MNRE) — primary ministry for solar + BESS policy
  • Central Electricity Authority (CEA) — technical standards, grid advisory
  • Central Electricity Regulatory Commission (CERC) — tariff and connectivity regulations
  • Ministry of Heavy Industries — PLI for ACC battery manufacturing
  • Power System Development Fund (PSDF) — funding conduit for VGF Scheme-II

Key Numbers

Parameter Figure Source
Peak demand record (Apr 25, 2026) 256.1 GW [1]
Solar share of installed capacity (early 2026) ~28% [1]
Solar share of peak-day generation (Apr 2026) 10.8% [1]
Solar curtailment (May–Dec 2025) 2.3 TWh [1]
VGF Scheme-I outlay ₹3,760 crore / 13,220 MWh [6]
VGF Scheme-II outlay ₹5,400 crore / 30,000 MWh [3]
Combined VGF BESS target ~43 GWh [3]
PLI for ACC (MHI) ₹18,100 crore / 50 GWh [5]
Grid-scale storage earmark (PLI) 10 GWh of 50 GWh [5]
BESS required by 2026–27 (NEP 2023) 34.72 GWh (BESS) + 47.65 GWh (PSP) = 82.37 GWh [2]
BESS required by 2031–32 (NEP 2023) 236 GWh [3]
VGF-I discovered tariff ₹10.18/kWh [7]
ESO trajectory 1% (FY24) → 4% (FY30) [2]
CEA co-location recommendation ≥10% of solar installed cap, ≥2 hours duration [2]

5. Multi-Dimensional Analysis

Economic

  • Solar curtailment of 2.3 TWh in 2025 represents direct fiscal waste — generators are compensated for power never delivered; costs ultimately borne by public exchequer and consumers. [1]
  • BESS reduces peak-hour power purchase costs for DISCOMs by arbitraging surplus midday solar into expensive evening peak demand.
  • VGF mechanism de-risks private investment; early discovered tariff of ₹10.18/kWh (BESS) expected to fall with PLI-driven domestic manufacturing. [7]
  • PLI for ACC (₹18,100 crore) targets creation of a domestic battery manufacturing ecosystem, reducing import dependence (currently >90% of lithium-ion cells imported from China). [5]

Environmental

  • 4,000 MWh BESS deployment projected to cut 1.3 million metric tonnes of CO₂ per year by displacing fossil peaker plants. [8]
  • Curtailment wastes clean electrons, effectively forcing grid operators to substitute with thermal generation — perverse environmental outcome.
  • India's NDC targets 500 GW non-fossil capacity by 2030; storage is structurally necessary to make this dispatchable and credible under UNFCCC commitments.

Geopolitical / Strategic

  • India's critical mineral vulnerability: lithium, cobalt, nickel for batteries largely sourced from geopolitically sensitive regions (DRC, Chile, China); domestic ACC manufacturing reduces supply-chain exposure.
  • Grid stability = national security — large-scale outages (as risked by unmanaged solar surplus) have cascading effects on defence, hospitals, water systems.
  • India's climate diplomacy (UNFCCC COP commitments, ISA leadership) depends on demonstrating that high-renewable grids are stable and reliable.

Scientific / Technological

  • Lithium Iron Phosphate (LFP) chemistry dominates grid-scale BESS for its safety and cycle life; competing chemistries (sodium-ion, flow batteries) are emerging for longer durations.
  • CEA's Draft Technical Standards for Construction of BESS Regulations, 2025 and Draft Safety Amendment Regulations standardise design, addressing fire-risk concerns. [2]
  • Co-location of BESS with solar parks (CEA advisory, Feb 2025) optimises land use and reduces transmission losses; minimum 2-hour duration target is a technical floor, not a ceiling.
  • CERC's September 2025 order enabling separate grid connectivity during non-solar hours allows storage-as-transmission arbitrage, a regulatory innovation. [2]

Administrative

  • DISCOM financial health is a bottleneck: weak DISCOMs cannot underwrite long-term BESS power purchase agreements (PPAs), deterring private investment.
  • VGF Scheme mandates that ≥85% of BESS output must first be offered to DISCOMs before being sold elsewhere — prioritises public utility over merchant trading. [9]
  • State-Centre coordination gap: States with high solar generation (Rajasthan, Gujarat, Tamil Nadu) lack authority to independently build inter-state storage infrastructure.
  • Permitting, land acquisition, and grid interconnection delays slow BESS project execution despite financial incentives.

6. Recent Developments (last 12–18 months)

  • February 2025: CEA issues advisory recommending co-location of ESS with solar projects at ≥10% capacity for ≥2 hours. [2]
  • 2025 (May–December): 2.3 TWh solar generation curtailed; 0.9 TWh wasted in October 2025 alone. [1]
  • June 2025: Government approves VGF Scheme-II — 30 GWh BESS, ₹5,400 crore from PSDF. [3]
  • September 2025: CERC allows separate grid connectivity during non-solar hours for storage-enabled projects. [2]
  • 2025 full year: India recorded its highest-ever annual renewable energy expansion (PIB, 2025). [10]
  • Draft BESS Safety Regulations 2025 (CEA): Published for public comment; standardises construction and safety norms. [2]
  • April 25, 2026: Solar meets 21.5% of afternoon load at 256.1 GW record demand — new operational benchmark. [1]

7. Prelims Hooks

  1. India's peak electricity demand record as of April 2026: 256.1 GW (April 25, 2026). [1]
  2. Solar's share of India's installed electricity capacity (early 2026): ~28% (up from ~15% in 2022). [1]
  3. Solar curtailment in India (May–December 2025): 2.3 TWh, equal to 18% of average monthly solar output. [1]
  4. VGF Scheme-I for BESS: approved March 2024, outlay ₹3,760 crore, target 13,220 MWh at ₹27 lakh/MWh. [6]
  5. VGF Scheme-II for BESS: approved June 2025, outlay ₹5,400 crore, target 30 GWh, funded from PSDF. [3]
  6. Combined BESS target under both VGF schemes: ~43 GWh. [3]
  7. PLI for Advanced Chemistry Cell (ACC): Ministry of Heavy Industries, outlay ₹18,100 crore, capacity 50 GWh; grid-scale storage earmark: 10 GWh. [5]
  8. BESS requirement per National Electricity Plan 2023 (CEA): 82.37 GWh by 2026–27 (34.72 GWh BESS + 47.65 GWh PSP); 236 GWh by 2031–32. [2][3]
  9. Energy Storage Obligation (ESO): 1% in FY 2023–24, rising to 4% by FY 2029–30 in 0.5%/year increments. [2]
  10. CEA co-location advisory (February 2025): BESS must be ≥10% of installed solar capacity for ≥2 hours duration. [2]
  11. VGF-I discovered tariff (first BESS bid): ₹10.18/kWh. [7]
  12. Carbon emission reduction from 4,000 MWh BESS deployment: 1.3 million metric tonnes/year. [8]
  13. Implementing ministry for BESS/solar storage policy: Ministry of New and Renewable Energy (MNRE). [2]
  14. ≥85% of VGF-funded BESS output must first be offered to DISCOMs before sale to others. [9]
  15. CERC order (September 2025): Allows separate grid connectivity during non-solar hours to enable storage-based power shifting to evening/night. [2]

8. Mains Relevance

GS Paper mapping:

  • GS-III: Infrastructure (Energy); Science & Technology; Environment & Ecology (climate, emissions)
  • GS-II: Government policies and interventions (VGF, PLI, ESO); role of regulatory bodies (CERC, CEA)

Specific syllabus headings:

  • Conservation, environmental pollution and degradation
  • Infrastructure: Energy
  • Effects of liberalization on the economy, changes in industrial policy and their effects on industrial growth
  • Government Budgeting (VGF mechanisms)

Plausible Mains question stems:

  1. "India's solar energy ambitions are hostage to its battery storage deficit." Critically examine the policy measures taken so far and the structural challenges that remain. (GS-III, 15 marks)

  2. "The curtailment of renewable energy is not merely a technical failure but a governance and regulatory challenge." Discuss with reference to India's BESS policy ecosystem. (GS-II/III, 15 marks)

  3. "Achieving India's 500 GW non-fossil capacity target by 2030 without commensurate energy storage investment risks fiscal and grid-stability consequences." Analyse. (GS-III, 10 marks)


9. Related Topics to Study Next

Topic Connection
India's Renewable Energy Targets (500 GW by 2030) Storage is structurally necessary to make the capacity target operationally meaningful
National Electricity Plan (NEP) 2023 Primary planning document quantifying BESS requirements (82.37 GWh by 2026–27)
Critical Minerals Mission / Lithium reserves Battery supply chains depend on lithium, cobalt, nickel — India's domestic deposits and import diplomacy
India's NDC and Net-Zero 2070 commitment Storage enables credibility of high-renewable grid under UNFCCC pledges
CERC and Electricity Act 2003 Regulatory framework under which BESS tariffs, grid access, and ESO are notified
DISCOMs — financial health and reform (RDSS) Weak DISCOMs cannot sign long-term BESS PPAs; DISCOM reform is a prerequisite for storage scale-up
Production-Linked Incentive (PLI) Scheme Cross-sector scheme; ACC PLI is India's bet on domestic battery manufacturing to reduce China dependency
Pumped Storage Hydro (PSH) Complementary long-duration storage to BESS; CEA plan integrates both

10. Common Errors / Trap Areas

  1. Wrong ministry for PLI-ACC: The PLI scheme for Advanced Chemistry Cell battery manufacturing is under Ministry of Heavy Industries, NOT MNRE — a frequent confusion since the end-use is renewable energy.

  2. Conflating installed capacity share with generation share: Solar is ~28% of installed capacity but only ~10.8% of actual generation on the peak day — UPSC options routinely exploit this distinction.

  3. VGF Scheme-I vs Scheme-II details: Scheme-I (March 2024) = 13,220 MWh at ₹27 lakh/MWh; Scheme-II (June 2025) = 30 GWh at ₹18 lakh/MWh from PSDF. Mixing up capacities, costs, or funding sources is a common error.

  4. ESO vs RPO confusion: Renewable Purchase Obligation (RPO) mandates purchase of renewable energy; Energy Storage Obligation (ESO) mandates purchase specifically from storage-backed supply — these are distinct instruments with different trajectories.

  5. Curtailment = waste, not conservation: Exam options may frame curtailment as intentional energy saving or grid management efficiency. It is in fact an economic and environmental loss — generators are compensated for power that is never consumed, burdening the exchequer.


Sources

  1. 1"Building bridges — Battery storage capacity must keep pace with solar energy generation" — The Hindu, May 6, 2026tier 4
  2. 2"Development and Deployment of Energy Storage Capacities to Power Reliable Renewable Future" — PIB, 2025pib.gov.in · tier 1
  3. 3"Government Takes Multi-Pronged Steps to Scale Up Energy Storage Capacity in the Country" — PIBpib.gov.in · tier 1
  4. 4"Energy Storage System Roadmap for India: 2019–2032" — NITI Aayog — )-Roadmap-for-India-2019-2032.pdfniti.gov.in · tier 1
  5. 5"Cost of energy storage discovered in bid is ₹10.18/kWh; VGF and PLI for battery energy storage expected to bring down cost" — PIBpib.gov.in · tier 1
  6. 6"Cabinet approves the Scheme titled Viability Gap Funding for development of Battery Energy Storage Systems (BESS)" — PIBpib.gov.in · tier 1
  7. 7"Cost of energy storage discovered in bid is 10.18 rupees per kilowatt hour" — PIBpib.gov.in · tier 1
  8. 8"Development of 4,000 MWh Battery Energy Storage System expected to reduce carbon emissions by 1.3 MMT/year" — PIBpib.gov.in · tier 1
  9. 9"At least 85% of power from VGF-funded BESS projects to be first offered to Discoms" — PIBpib.gov.in · tier 1
  10. 10"2025 Marks Highest-Ever Renewable Energy Expansion in India's Energy Transition Journey" — PIBpib.gov.in · tier 1
At the end · practice MCQs
5 questions on this article
Check the answer for each question, or reveal all at once.
Practice MCQs →

Mains Q&A on this note

Also on 6 May

All 6 May articles →