UPSC Prelims Practice Questions — AI data-centre boom puts power grid under pressure
Q1. With reference to the load despatch architecture under the Electricity Act, 2003, consider the following statements: Which of the statements given above is/are correct?
- A dispute over a direction issued by a Regional Load Despatch Centre for the integrated operation of the regional grid is referred to the Central Electricity Regulatory Commission.
- A dispute over a direction issued by a State Load Despatch Centre for the security of the intra-State grid is also referred to the Central Electricity Regulatory Commission, since grid security is a national concern.
- A State Load Despatch Centre is barred from engaging in the business of trading in electricity.
- A. 1 only
- B. 1 and 3 only
- C. 1, 2 and 3
- D. 2 and 3 only
Q2. Electricity is a subject in the Concurrent List. Suppose a State Legislature passes a law under which the State's load despatch centre need not follow certain directions issued under the Electricity Act, 2003, a law Parliament made earlier. In this context, consider the following statements: Which of the statements given above is/are correct?
- If the State law is not reserved for the President's consideration, its conflicting provision is void to the extent of the repugnancy.
- If the State law is reserved for the consideration of the President and receives assent, it can prevail in that State.
- Once the State law has received Presidential assent, Parliament cannot later amend or repeal the State provision on that matter.
- A. 1 only
- B. 2 and 3 only
- C. 1 and 2 only
- D. 1, 2 and 3
Q3. Suppose a large cluster of AI data centres connected to India's synchronous national grid suddenly raises its power draw, and generation does not respond immediately. Consider the following statements: Which of the statements given above are correct?
- System frequency would tend to fall below its nominal value.
- The frequency deviation would be felt across the synchronous grid, not only in the State where the data centres are located.
- System frequency would tend to rise, because the extra load draws energy from generator rotors and speeds them up.
- Fast-responding resources such as battery storage could help limit the deviation by injecting power quickly.
- A. 1, 2 and 4 only
- B. 2, 3 and 4 only
- C. 1, 2, 3 and 4
- D. 1 and 3 only
Q4. Consider the following statements: Which of the following is correct in respect of the above statements?
- Since the Southern regional grid was synchronised with the rest of India's grid at the end of 2013, a sudden loss of a large generating unit in the Southern region can lower the frequency seen by consumers in the Northern region.
- In a synchronous grid, all interconnected generators rotate in step at one common frequency, so an imbalance at any point affects the frequency of the whole interconnected system.
- A. Both Statement-I and Statement-II are correct and Statement-II explains Statement-I
- B. Both Statement-I and Statement-II are correct, but Statement-II does not explain Statement-I
- C. Statement-I is correct, but Statement-II is incorrect
- D. Statement-I is incorrect, but Statement-II is correct
Q5. Consider the following statements: Which of the following is correct in respect of the above statements?
- A State Load Despatch Centre, although the apex body for integrated operation of the State's power system, must comply with the directions of the Regional Load Despatch Centre.
- State Load Despatch Centres are operated by Grid Controller of India Ltd., the same company that operates the Regional Load Despatch Centres.
- A. Both Statement-I and Statement-II are correct and Statement-II explains Statement-I
- B. Both Statement-I and Statement-II are correct, but Statement-II does not explain Statement-I
- C. Statement-I is correct, but Statement-II is incorrect
- D. Statement-I is incorrect, but Statement-II is correct
Q6. With reference to the SCADA/EMS systems used at load despatch centres, consider the following statements: Which of the statements given above is/are correct?
- SCADA mainly collects real-time telemetry from substations and generating stations and lets control-room operators send remote commands.
- An EMS is a field device at substations that physically trips circuit breakers when a fault occurs, independently of the control centre.
- Because SCADA/EMS is largely a software system, the cost of upgrading it is insulated from global demand for servers and semiconductors.
- A. 1 and 2 only
- B. 1, 2 and 3
- C. 2 and 3 only
- D. 1 only
Q7. Expanding the inter-regional transfer capacity of a single synchronous national grid helps a country integrate variable renewable energy mainly because
- A. it isolates each region electrically at its boundary, so that renewable fluctuations remain confined to the region of origin.
- B. it raises the nominal frequency of the grid, allowing generators to absorb larger swings in renewable output without tripping.
- C. it lets surplus solar or wind output in resource-rich regions meet demand in other regions, evening out local variability.
- D. it allows States to dispense with their own load despatch centres, since all scheduling shifts to a single national centre.
Q8. With reference to how the cost of grid upgrades driven by the growth of AI data centres is recovered in India, consider the following statements: Which of the statements given above is/are correct?
- Approved capital costs of a transmission-system upgrade are recovered from network users only gradually, over the asset's useful life, rather than as a single upfront charge.
- Because transmission charges are pooled across users of the network, consumers who use no data-centre services may still bear part of the cost of upgrades.
- A rise in global prices of grid-control hardware can raise transmission charges even for consumers whose own electricity use has not changed.
- A. 1, 2 and 3
- B. 1 and 3 only
- C. 1 and 2 only
- D. 2 and 3 only