UPSC Prelims Practice Questions — Indian Railways Speeds Up Kavach 4.0 Safety Rollout with 472 km Commissioned Across Three Sections
Q1. Which of the following is/are correctly identified as core safety functions of the Kavach system?
- Prevention of Signal Passed at Danger (SPAD).
- Automatic application of brakes when a train over-speeds.
- Automatic issuance of e-tickets to onboard passengers.
- Protection against head-on and rear-end train collisions.
- A. 1 and 3 only
- B. 1, 2 and 4 only
- C. 2 and 4 only
- D. 1, 2, 3 and 4
Q2. With reference to the evolution of the Kavach system, which one of the following statements is NOT correct?
- Kavach originated from the Train Collision Avoidance System (TCAS) developed with Indian manufacturers.
- Kavach was adopted as the National ATP system in July 2020.
- The Kavach Version 4.0 specification was approved by RDSO in July 2024.
- Kavach Version 4.0 was first commissioned in the year 2020 on the Vadodara–Virar section.
- A. 1 only
- B. 2 and 3 only
- C. 3 only
- D. 4 only
Q3. Regarding the development history of Kavach, which of the statements given above is/are correct?
- The precursor TCAS was developed by RDSO in association with three Indian firms.
- RDSO approved the Kavach Version 4.0 specification on 16 July 2024.
- Following the Version 4.0 approval, Kavach 4.0 was first commissioned on the Sawai Madhopur–Kota section.
- Field trials of Kavach on passenger trains began in the year 2012.
- A. 1, 2 and 3 only
- B. 1 and 4 only
- C. 2, 3 and 4 only
- D. 1, 2, 3 and 4
Q4. With reference to the Kavach 4.0 commissioning of 30 January 2026, which of the following section-and-figure pairs is/are correctly identified?
- Vadodara–Virar — 344 km
- Tuglakabad Junction Cabin–Palwal — 35 km
- Manpur–Sarmatanr — 93.3 km
- Total route km commissioned on that single day — 738 km
- A. 1, 2 and 3 only
- B. 1 and 4 only
- C. 2, 3 and 4 only
- D. 1, 2, 3 and 4
Q5. Which one of the following became the first Kavach-equipped train to run from Mumbai?
- A. Train No. 20907 Dadar–Bhuj Sayajinagri Express
- B. Train No. 12951 Mumbai–New Delhi Rajdhani Express
- C. Mumbai–Gandhinagar Vande Bharat Express
- D. Deccan Queen Express
Q6. With reference to the three sections where Kavach 4.0 was commissioned on 30 January 2026, which of the statements given above is/are correct?
- Vadodara–Virar section lies on the Western Railway.
- Tuglakabad Junction Cabin–Palwal section lies on the Northern Railway.
- Manpur–Sarmatanr section lies on the East Central Railway.
- The Tuglakabad Junction Cabin–Palwal section, at 35 km, was the longest of the three sections commissioned.
- A. 1, 2 and 3 only
- B. 2 and 4 only
- C. 1, 3 and 4 only
- D. 1, 2, 3 and 4
Q7. Among the sections on which Kavach 4.0 was commissioned on 30 January 2026, which one was the longest by route kilometres?
- A. Vadodara–Virar (344 km)
- B. Manpur–Sarmatanr (93.3 km)
- C. Tuglakabad Junction Cabin–Palwal (35 km)
- D. Howrah–Bardhaman (105 km)
Q8. With reference to the institutional framework of the Kavach programme, which one of the following statements is NOT correct?
- The Ministry of Railways is the implementing ministry for Kavach.
- RDSO, headquartered at Lucknow, developed the Kavach specification.
- Kavach was developed in association with three Indian firms/OEMs.
- The Kavach technical specification is approved by NITI Aayog.
- A. 1 only
- B. 2 and 3 only
- C. 3 only
- D. 4 only
Q9. The technical specification of Kavach Version 4.0 was approved by which one of the following bodies?
- A. Research Designs and Standards Organisation (RDSO)
- B. Centre for Railway Information Systems (CRIS)
- C. RailTel Corporation of India
- D. Indian Railways Institute of Signal Engineering and Telecommunications (IRISET)
Q10. The Kavach 4.0 rollout — first commissioned on the Sawai Madhopur–Kota section and later expanded to the Palwal–Mathura–Nagda and Howrah–Bardhaman sections — is operationalised on the ground primarily by which one of the following?
- A. Zonal Railways under the Ministry of Railways
- B. Dedicated Freight Corridor Corporation of India Ltd (DFCCIL)
- C. National High Speed Rail Corporation Ltd (NHSRCL)
- D. Delhi Metro Rail Corporation (DMRC)
Q11. With reference to Kavach and its comparison with global Automatic Train Protection systems, which one of the following statements is NOT correct?
- Kavach is certified to Safety Integrity Level 4 (SIL-4), the highest safety integrity level.
- Like the European ETCS, Kavach is an Automatic Train Protection (ATP) system.
- Kavach uses trackside RFID tags and UHF radio communication.
- Kavach is an imported system licensed from the European ERTMS/ETCS consortium.
- A. 1 only
- B. 2 and 3 only
- C. 1 and 3 only
- D. 4 only