UPSC Prelims Practice Questions — Harnessing Small Hydro Power

Q1. With reference to the classification of hydro power in India, consider the following statements: Which of the statements given above is/are correct?

  1. Whether a project of 20 MW installed capacity counts as small hydro depends on whether it uses a dam or a run-of-the-river diversion.
  2. Since 2019, hydro projects above 25 MW are also treated as a renewable energy source, so renewable status alone does not distinguish small hydro from large hydro.
  3. Distribution companies can meet a separate Hydropower Purchase Obligation, carved out within the non-solar Renewable Purchase Obligation, with power from large hydro projects commissioned after the 2019 measures.
  • A. 2 and 3 only
  • B. 1 and 2 only
  • C. 1 and 3 only
  • D. 1, 2 and 3

Q2. Consider the following statements: Which of the following is correct in respect of the above statements?

  1. Small hydro plants can be built in plains regions where rivers have very gentle natural gradients.
  2. Drops in the water level along irrigation canals provide the head needed to drive turbines, and the water is returned to the canal after generation.
  • A. Both Statement-I and Statement-II are correct and Statement-II explains Statement-I
  • B. Both Statement-I and Statement-II are correct, but Statement-II does not explain Statement-I
  • C. Statement-I is correct, but Statement-II is incorrect
  • D. Statement-I is incorrect, but Statement-II is correct

Q3. A State plans small hydro projects at three types of site: (i) an existing irrigation barrage with a marked drop between its upstream pool and downstream channel; (ii) a steep mountain stream with no storage; (iii) a network of irrigation canals in the plains with periodic falls. Consider the following statements: Which of the statements given above is/are correct?

  1. A plant at site (i) would first need a new storage reservoir to be impounded before it could generate.
  2. A run-of-the-river plant at site (ii) would see its output vary with the seasonal flow of the stream.
  3. Canal-fall plants at site (iii) would keep generating at full output while the canals are closed for maintenance or outside the irrigation season.
  • A. 2 and 3 only
  • B. 1 and 2 only
  • C. 1 and 3 only
  • D. 2 only

Q4. Consider the following statements: Which of the following is correct in respect of the above statements?

  1. Small hydro plants located near consumers in remote hilly areas can reduce transmission and distribution losses.
  2. Unlike solar plants, run-of-the-river small hydro plants generate at a uniform output across all seasons.
  • A. Both Statement-I and Statement-II are correct and Statement-II explains Statement-I
  • B. Both Statement-I and Statement-II are correct, but Statement-II does not explain Statement-I
  • C. Statement-I is correct, but Statement-II is incorrect
  • D. Statement-I is incorrect, but Statement-II is correct

Q5. Consider the following assertion: As the share of solar and wind power in India's grid rises, renewable sources that can supply firm and flexible output, such as hydro, become more valuable. Which of the statements given above support/supports the assertion?

  1. Solar output falls to zero after sunset, often when electricity demand peaks in the evening.
  2. Sudden changes in wind and solar output have to be balanced by sources whose generation can be adjusted quickly, so that grid frequency stays stable.
  3. Adding hydro capacity removes the need to build transmission lines for evacuating solar and wind power.
  • A. 2 and 3 only
  • B. 1 and 2 only
  • C. 1, 2 and 3
  • D. 1 only

Q6. With reference to environmental flows in the context of hydro power, consider the following statements: Which of the statements given above is/are correct?

  1. An environmental flow is a minimum quantity of water that must be maintained in a river downstream of a dam or diversion so that its ecological integrity is sustained.
  2. Mandatory environmental-flow releases can reduce the electricity a diversion-based project generates in the lean season.
  3. A series of diversion projects on one stream can leave several stretches with reduced flow even if each project is individually small.
  • A. 1 and 2 only
  • B. 1 and 3 only
  • C. 1, 2 and 3
  • D. 2 and 3 only

Q7. Under the SHP Development Scheme, central financial assistance for a project is the lower of a fixed amount per MW and a fixed percentage of project cost, subject to an absolute ceiling per project; the percentage and the ceiling are higher for North-Eastern States and International Border Districts. Consider the following statements: Which of the statements given above is/are correct?

  1. Of two projects of equal capacity in the same category, the one with the lower project cost can receive less assistance, because the percentage-of-cost limit may be lower than the per-MW limit.
  2. Once a project is large enough for the per-project ceiling to bind, adding further capacity to it raises the central assistance it receives.
  3. A per-project ceiling limits how much of the fixed scheme outlay any single large project can absorb.
  • A. 1 and 2 only
  • B. 1 and 3 only
  • C. 2 only
  • D. 1, 2 and 3