Critically evaluate the Carbon Credit Trading Scheme as an instrument for industrial decarbonisation in India, with special reference to the cement sector.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
The Ministry of Power and MoEFCC developed the Carbon Credit Trading Scheme (CCTS) together. It aims to decarbonise the economy by putting a price on greenhouse gas emissions through tradable Carbon Credit Certificates (CCCs) [3]. Cement produces about 6–7% of India's GHG emissions [1], which makes it the scheme's hardest test.
Strengths
- Market efficiency: Plants that beat their GHG Emission Intensity (GEI) targets earn CCCs, and plants that miss them must buy CCCs. This means emissions get cut first wherever cutting is cheapest [2].
- Fast, phased coverage: Cement was one of the first four sectors notified in October 2025 (282 entities). By January 2026, coverage had grown to 490 entities [2].
- Builds on existing institutions: Sectors moved over from the PAT scheme. BEE acts as administrator and Grid India as registry [4].
- Room for growth: Targets are set per tonne of output. This lets cement output grow for Viksit Bharat 2047 while emissions per tonne fall.
- Trade protection: A domestic carbon price strengthens India's position against the EU's CBAM. CBAM covers cement, and importers start paying it in 2026 [6].
Weaknesses (cement focus)
- No absolute cap: Targets limit emissions per tonne, not in total [2]. Cement output is projected to rise about sevenfold by 2070 [1], so total emissions can still grow.
- Process emissions are left out: About 55% of the sector's emissions come from limestone calcination [1]. Efficiency gains and renewable power cannot remove these.
- Ambition gap: Carbon intensity must fall from 0.63 to about 0.09–0.13 tCO₂e per tonne by 2070, a cut of roughly 80–85% [1]. Small near-term cuts would leave too many credits in the market and keep prices low.
- Finance gap: A low credit price cannot pay for CCUS (carbon capture, utilisation and storage). NITI Aayog estimates industry alone needs about $6.1 trillion of the $22.7 trillion required for net zero [5].
- Measurement burden: The scheme is only credible if monitoring, reporting and verification (MRV) are robust across hundreds of plants.
Verdict: CCTS is a sound foundation, but on its own it is not enough to decarbonise cement.
CCTS has made carbon pricing part of how Indian industry is governed. However, its intensity-based design does not yet match the scale of cement's process emissions. The way forward:
- Publish a schedule of steadily tighter GEI targets, moving towards an absolute cap over time.
- Combine the scheme with the main levers in NITI Aayog's roadmap: refuse-derived fuel (RDF), clinker substitution and CCUS [1].
- Back these with dedicated climate finance [5].
With these steps, CCTS can support India's net-zero 2070 pledge and SDG 13.
Sources
- 1NITI Aayog, Roadmap for Cement Sector Decarbonisation (2026): cement's 6–7% share of GHG emissions, 55% from calcination, about sevenfold output rise by 2070, intensity falling from 0.63 to 0.09–0.13 tCO₂e per tonne, RDF/clinker/CCUS/CCTS levers
- 2PIB, "Government notifies Greenhouse Gas Emission Intensity Targets for 208 more Carbon-intensive Industries": GEI targets, how credits are earned and traded, October 2025 notification of four sectors (282 entities), coverage of 490 entities
- 3PIB, "Ministry of Power & Ministry of Environment, Forests & Climate Change to develop Carbon Credit Trading Scheme for Decarbonisation": joint development by MoP and MoEFCC, pricing GHG emissions through CCCs
- 4PIB, "Framework for Carbon Credit Trading Scheme (CCTS)": move from PAT, BEE as administrator, Grid India as registry
- 5NITI Aayog, Scenarios Towards Viksit Bharat and Net Zero, Vol. 9: Financing Needs (2026): $22.7 trillion net-zero investment, of which about $6.1 trillion is for industry
- 6European Commission, Carbon Border Adjustment Mechanism: CBAM covers cement, and payments start in 2026