Discuss how the Defence Acquisition Procedure 2020 prioritises indigenous design and development. Assess its impact on India's defence-industrial base, with examples.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →The Defence Acquisition Procedure (DAP) 2020 came into force on 1 October 2020. It changed the default in capital procurement from "buy global" to "design and make in India" [1]. It has made domestic industry stronger, but India still depends on imports and its research base remains weak.
How DAP 2020 prioritises indigenous design
- Buy (Indian-IDDM) (Indigenously Designed, Developed and Manufactured) is the top-priority category for capital buys [1].
- Indigenous content (IC) rose to at least 50%, up from 40% under DPP 2016 [1]. A November 2023 amendment applied 50% IC to all categories [2].
- Reserved categories: IDDM, Make-I/II and the Strategic Partnership model are open only to Indian-controlled firms with FDI of 49% or less [1].
- Indigenous software is to be explored for fire-control systems, radars and encryption [1].
- Supporting tools: the Positive Indigenisation Lists put 5,012 items under a phased import ban. DRDO's Technology Development Fund has sanctioned 78 projects worth Rs 333 crore for Indian firms, including MSMEs [2].
Impact on the defence-industrial base
Gains
- Assured orders: MoD signed a Rs 661.50 crore Buy (Indian-IDDM) contract with BrahMos Aerospace for naval fire-control systems and launchers. It requires 68% IC and involves MSMEs [3].
- Steady pipeline: in 2023 the Defence Acquisition Council approved BrahMos launchers for Shivalik-class ships and Next Generation Missile Vessels [4].
- Exports: defence exports reached Rs 21,083 crore in 2023-24 [2]. BrahMos, co-developed with Russia, has found a buyer in the Philippines [5].
- Import substitution: 61% of the items on the indigenisation lists are now made in India [2].
Limits
- Imports remain high: India took 10% of global arms imports in 2013–23, and 28% of modernisation spending still goes abroad [2].
- Slow procurement: the Standing Committee on Defence (2024) said MoD's 19–26 month acquisition cycle is too long [2]. The BrahMos launcher order took three years from approval in 2023 to contract.
- Weak R&D: CAG found that 119 of 178 DRDO projects overran their timelines [2].
- IC is only a cost share: a high IC figure can still hide imported critical parts such as seekers and engines.
- Funding gap: capital outlay is only about 28% of the defence budget [2].
DAP 2020 has turned Aatmanirbhar Bharat into a binding procurement rule, and Indian firms now get both orders and design roles. To build on this, India needs:
- faster approval-to-contract for repeat buys,
- the non-lapsable Defence Modernisation Fund recommended by the 15th Finance Commission [2],
- R&D money directed at critical subsystems.
This would make self-reliance real strategic autonomy and not just a percentage on paper.
Sources
- 1Raksha Mantri Shri Rajnath Singh unveils Defence Acquisition Procedure (PIB, 2020)IDDM top priority, 50% vs 40% IC, reservation for Indian vendors, indigenous software
- 2Demand for Grants 2025-26 Analysis: Defence (PRS Legislative Research)Nov 2023 IC amendment, indigenisation lists, Technology Development Fund, exports, import share, acquisition timeline, CAG on DRDO, capital outlay, 15th Finance Commission fund
- 3MoD signs Rs 661 crore contract to procure BrahMos Fire Control System and Launchers for Indian Navy ships (PIB, 6 Oct 2026)Buy (Indian-IDDM) contract, 68% IC, MSME participation
- 4Ministry of Defence – Year End Review 2023 (PIB)2023 approval for BrahMos launchers for Shivalik-class ships and NGMVs
- 5From Strategic Partnership to Special and Privileged Bond: India-Russia Relations at a Glance (PIB)BrahMos co-development and export to the Philippines