Offshore wind can be the next frontier of India's energy transition. Examine the policy framework and the challenges involved.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
Offshore wind farms are built at sea, where winds are stronger and steadier, and offshore turbines can reach about 15 MW each [1]. NIWE estimates 36 GW of potential off Gujarat and nearly 35 GW off Tamil Nadu [1]. Onshore wind is held back by land and Right-of-Way problems, so offshore wind is a logical next frontier. However, the policy framework is well ahead of what has actually been built.
Policy Framework
- National Offshore Wind Energy Policy was notified on 6 October 2015. MNRE is the nodal ministry. NIWE, Chennai is the nodal agency for resource assessment and surveys in the EEZ [1].
- Offshore Wind Energy Strategy (2023) sets a 37 GW bidding trajectory by 2030. The Offshore Wind Energy Lease Rules, 2023 (19 December 2023) govern how seabed is allotted [1].
- Viability Gap Funding (VGF): ₹6,853 crore for 1 GW (500 MW each off Gujarat and Tamil Nadu), plus ₹600 crore to upgrade two ports. PGCIL will build the transmission links [3].
- Development models: Model A uses government-led studies plus VGF. Models B and C are developer-led and get no central financial help [1].
- Partnerships: the India–Denmark MoU (2019, renewed May 2025) and the India–UK Offshore Wind Taskforce (2026) bring in technical know-how [2].
Challenges
- Funding gap: VGF covers 1 GW of a 37 GW plan [1][3]. The 4 GW Tamil Nadu tender is on open-access terms with no VGF [4].
- Cost and infrastructure: large turbines need specialised ports, installation ships and undersea cables, so they cost much more than onshore projects [1]. The port grant covers only two ports [3].
- Execution lag: in 2022 the Standing Committee on Energy noted about 70 GW of offshore potential and not a single project [5].
- Payment risk: DISCOMs owed wind developers ₹14,247 crore in overdue payments (March 2022) [5]. This makes lenders see the sector as risky and raises the cost of capital.
India has a strong plan for offshore wind but limited money and infrastructure behind it. The way forward is to:
- extend the 500 MW Contracts-for-Difference pilot [2] to offshore blocks;
- release VGF in phases linked to falling costs;
- build a port-and-vessel ecosystem on India's ~24 GW turbine manufacturing base [2];
- enforce timely DISCOM payments.
Done this way, offshore wind can become a real frontier and advance SDG 7 and India's net-zero 2070 goal.
Sources
- 1MNRE: Offshore Wind2015 policy, NIWE as nodal agency, Gujarat/Tamil Nadu potential, 2023 strategy (37 GW), Lease Rules 2023, development models, turbine size
- 2PIB: Global Wind Day 2026, Charting India's Path to 100 GW and BeyondIndia–Denmark MoU, India–UK Taskforce, CfD pilot, manufacturing capacity
- 3PIB: Cabinet approves VGF scheme for Offshore Wind Energy Projects₹6,853 crore for 1 GW, ₹600 crore port grant, PGCIL transmission
- 4PIB: Government invites bids for 4 GW Offshore Wind Energy Projects off Tamil Naduopen-access tender with no VGF
- 5PRS: Report Summary, Evaluation of Wind Energy in India (Standing Committee on Energy, 2022)~70 GW offshore potential with no projects; ₹14,247 crore DISCOM dues
Practice
5 questions on this item
Check the answer for each question, or reveal all at once.