·PIB·15 marks·250–350 words

Production Linked Incentive schemes have drawn strong bidding interest but have been slow to commission capacity. Critically evaluate with reference to the ACC battery programme.

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. Strengths: interest is real and the design is sound
  2. Weaknesses: why factories lag behind bids

The National Programme on Advanced Chemistry Cell (ACC) Battery Storage was approved in May 2021 with an outlay of ₹18,100 crore. It targets 50 GWh of domestic cell capacity [1]. Its record shows the PLI paradox. Bids have far exceeded the capacity on offer. Yet of the 40 GWh awarded to four firms, only about 1 GWh had been installed by February 2026 [2].

Strengths: interest is real and the design is sound

  • Strong investor signal: in Round-1, 10 firms bid for about 130 GWh [3]. The 2026 tranche of 10 GWh for grid-scale storage drew 22 bids [4].
  • Fiscal prudence: the incentive is paid only on cells actually made and sold [1]. If a firm does not deliver, the government pays nothing.
  • Transparent procurement: selection is through a global, two-stage, online Quality and Cost Based Selection (QCBS) on the CPP Portal [4]. Quality counts alongside price.
  • Strategic logic: making cells at home reduces dependence on foreign supply chains. This serves energy security and technological self-reliance [4].

Weaknesses: why factories lag behind bids

  • A bid is not a factory: a bid is a paper promise. Problems with land, technology, skilled workers and raw materials appear only after the award [2].
  • Hard design rules: each firm needed a plant of at least 5 GWh and 60% domestic value addition within five years [1]. Only large firms could take that risk, and many had never made cells. Meeting 60% also needs a mineral and materials supply chain that India does not yet have.
  • Few strong bidders: Round-2 ended with only one beneficiary selected [2].
  • Supply and demand are not linked: the Ministry of Power's VGF Tranche-II funds 30 GWh of battery storage with ₹5,400 crore [5]. These projects go to the lowest bidder, with no link to cells made under PLI.
  • Delay has a cost: the budget is protected, but every year of delay deepens dependence on imported cells.

Verdict: the scheme's aim is sound, but its execution has been weak. Bidding interest shows the PLI idea is viable. Slow commissioning shows the scheme needs better follow-through.

Strong bidding supports the PLI approach, while slow commissioning points to gaps in execution. The way forward:

  • give more technical marks under QCBS for proven manufacturing experience;
  • set dated, publicly checked milestones from land to commercial production;
  • introduce a gradual domestic-cell preference in VGF tenders;
  • use the National Critical Mineral Mission to build the upstream supply chain.

Importing cells now for speed while building capacity at home for security would align the programme with SDG 7 and Viksit Bharat @2047 [4].

Sources

  1. 1PIB: Cabinet approves Production Linked Incentive scheme "National Programme on Advanced Chemistry Cell Battery Storage" (12 May 2021)outlay, 50 GWh target, minimum 5 GWh plant, 60% domestic value addition, incentive paid on sales
  2. 2PIB, Ministry of Heavy Industries: PLI ACC scheme status, Round-2 (February 2026)40 GWh awarded to four firms, about 1 GWh installed, Round-2 selected one beneficiary
  3. 3PIB, Ministry of Heavy Industries: 10 bids with capacity of about 130 GWh received under PLI ACC scheme (January 2022)Round-1 bidding response
  4. 4PIB, Ministry of Heavy Industries: MHI receives 22 bids for 10 GWh Advanced Chemistry Cell manufacturing capacity under PLI ACC Scheme (November 2026)22 bids, two-stage QCBS on the CPP Portal, energy security and self-reliance, Viksit Bharat @2047
  5. 5PIB: Viability Gap Funding for Battery Energy Storage Systems, Tranche-II (June 2025)₹5,400 crore for 30 GWh of battery storage