·The Hindu·15 marks·250–350 wordsGeographyPolityEconomy

River-interlinking projects promise water security but often trigger ecological and social costs. Discuss with reference to the Ken-Betwa Link Project.

In this answer
  1. The water-security promise
  2. Ecological costs
  3. Social costs

The Ken-Betwa Link Project (KBLP), cleared by the Union Cabinet in 2021 at ₹44,605 crore, is the first link under the 1980 National Perspective Plan to reach implementation [1]. It embodies the central dilemma of interlinking: assured water for a parched region weighed against submerged forests and uprooted communities.

The water-security promise

  • Transfers "surplus" Ken water to the deficit Betwa basin, serving chronically drought-prone Bundelkhand — ten districts of Madhya Pradesh and Banda, Mahoba, Lalitpur and Jhansi in Uttar Pradesh [1].
  • Delivers annual irrigation of 10.62 lakh hectares, drinking water to about 62 lakh people, and 103 MW hydro plus 27 MW solar power [1].
  • Central support of ₹39,317 crore and the MP–UP agreement demonstrate cooperative federalism in resolving a long-contested basin claim [1].

Ecological costs

  • The Daudhan reservoir submerges roughly 9,000 hectares, including 4,141 ha of Panna Tiger Reserve core and 1,314 ha of buffer [2] — the very habitat rebuilt after tigers were locally lost there.
  • Extensive felling fragments forest connectivity; compensatory afforestation cannot replicate mature habitat within a project timeline.
  • The "surplus–deficit" premise itself is contested, since climate variability may unsettle the assumed flows.

Social costs

  • Ten villages and about 1,913 families face displacement from the submergence zone alone [2].
  • Tribal households in Panna and Chhatarpur allege forced relocation, demolitions and opaque application of the LARR Act, 2013, with unequal packages for submergence-affected and canal-affected families [3].
  • Sustained agitation — an 18-day hunger strike ended only after the administration ordered fresh verification of excluded families [4] — shows correction driven by protest rather than planning.

KBLP's benefits are real, but its costs fall disproportionately on forests and forest-dwellers. Front-loaded, transparent LARR compliance with land-for-land resettlement, independently audited wildlife mitigation, and consent secured before construction would let interlinking deliver water security without sacrificing ecological and constitutional commitments to tribal dignity.

Sources

  1. 1PIB — Cabinet approves Ken-Betwa Interlinking of Rivers Project (Dec 2021)project cost, ₹39,317 crore central support, irrigation/drinking water/power benefits, beneficiary districts
  2. 2PIB — Impact of Ken Betwa Project, Rajya Sabha reply (Ministry of Jal Shakti)9,000 ha submergence, 4,141 ha PTR core and 1,314 ha buffer, 10 villages and 1,913 affected families
  3. 3Down To Earth — Ken-Betwa River Link: Tribal Families in Madhya Pradesh Fight for Fair Compensation and Rehabilitationforced relocation, demolitions, LARR Act 2013 non-compliance, unequal compensation
  4. 4Down To Earth — Ken-Betwa Project Protest Leader Ends 18-Day Fast After Fresh Verification Order in MP Villages18-day hunger strike and post-protest verification of excluded families