Examine the challenges of rehabilitation and resettlement in large infrastructure projects affecting tribal populations in India.
In this answer
The Xaxa Committee (2014) noted that tribal communities bear a disproportionate share of development-induced displacement while gaining the least from such projects [4]. Protests around the ₹44,605-crore Ken-Betwa Link Project show that rehabilitation and resettlement (R&R) remains the weakest link in India's infrastructure push [1][5].
Legal and procedural gaps
- The LARR Act, 2013 mandates Social Impact Assessment, consent and a defined R&R entitlement schedule, but exemptions and varying state rules dilute these safeguards in practice [2].
- The Forest Rights Act, 2006 requires recognition of individual and community forest rights before diversion; claims often remain undecided when possession is taken [3].
Inadequate and inequitable compensation
- Awards are cash- and land-title-centric, ignoring commons — grazing land, minor forest produce — that the FRA recognises as livelihood rights [3].
- Differentiated packages breed conflict: in Ken-Betwa, submergence-affected and canal-affected families in Chhatarpur and Panna allege unequal treatment [5].
Livelihood and cultural dislocation
- Forest-dependent households are relocated into cash economies without skills or assets, producing what the Xaxa Committee described as post-displacement impoverishment and loss of social networks [4].
- Land-for-land is rarely feasible near project sites, and sacred groves and kinship ties are simply non-compensable.
Institutional and implementation deficits
- Faulty enumeration excludes tenants, landless labour and adult sons; correction is reactive — at Ken-Betwa, inclusion of left-out families was assured only after a prolonged hunger strike [5].
- R&R lags construction, as engineering milestones under an eight-year completion target dominate review [1].
R&R fails less from absent law than from weak sequencing and ownership. Settling FRA claims and completing resettlement before submergence, offering land-for-land with annuity and project-benefit sharing, and vesting monitoring in Gram Sabhas under PESA can align projects with Article 46 and SDG-10. Water security for Bundelkhand is legitimate; it must not be financed by tribal impoverishment.
Sources
- 1PIB, "Cabinet approves Ken-Betwa Interlinking of Rivers Project" (Dec 2021)project cost of ₹44,605 crore, components and eight-year implementation timeline
- 2The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Social Impact Assessment, consent and R&R entitlement framework
- 3The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006individual and community forest rights, including minor forest produce
- 4Report of the High Level Committee on Socio-Economic, Health and Educational Status of Tribal Communities (Xaxa Committee, 2014), Ministry of Tribal Affairsdisproportionate tribal displacement and post-displacement impoverishment
- 5The Hindu, "Why are there protests over the Ken-Betwa project?" (July 26, 2026)Chhatarpur/Panna protests, compensation disparity, and post-agitation assurance on rehabilitation inclusion