Cost overrun
FlashcardsQuick reviseKey facts. One by one.Start →Also called: Time and cost overrun · Topic: Infrastructure: Transport, Communications and Energy · NCERT: Beyond NCERT
Meaning
A cost overrun is the amount by which a project's final or expected cost is higher than the cost approved at the start. It usually comes with a time overrun, which means the project finishes later than planned. Common causes are slow land acquisition, late clearances, design changes and rising prices of inputs. The longer a project is delayed, the more it usually costs.
Cost overrun (%) = (Anticipated cost − Original cost) ÷ Original cost × 100
This matters because public money gets tied up for longer and the benefits of the project arrive late. The Ministry of Statistics and Programme Implementation (MoSPI) tracks the cost and time of every Central infrastructure project costing ₹150 crore or more. Its online tracking portal is called PAIMANA.
Example
A highway is approved at ₹1,000 crore. Land disputes delay it, and it now needs ₹1,200 crore. That is a cost overrun of 20%. On a much bigger scale, MoSPI's December 2023 report covered 1,820 Central projects. Their expected cost was 18.65% above the original cost, which comes to about ₹4.83 lakh crore extra. Of these projects, 848 were delayed, by 36.59 months on average.
Don't confuse with
- Time overrun: This counts the delay in months beyond the planned finish date. A cost overrun counts the extra money in rupees or as a percentage. A project can have one without the other, but they usually go together.