Green Energy Open Access Rules, 2022
Also called: GEOA Rules · Topic: Infrastructure: Transport, Communications and Energy · NCERT: Beyond NCERT
Meaning
The Green Energy Open Access Rules, 2022 are central rules issued by the Ministry of Power under the Electricity Act 2003. Open access means a consumer can use the public power lines to buy electricity from any supplier, not only from the local DISCOM (the state electricity distribution company). The rules make it easier for firms to buy green power directly.
- They cut the minimum load for green open access from 1 MW to 100 kW, so smaller firms can also take part.
- They keep the cross-subsidy surcharge (CSS), a fee open-access buyers pay to the DISCOM to make up for the extra income it loses when a high-paying customer leaves. But for 12 years from the start of the project, CSS cannot rise by more than 50% of the rate in the year open access was granted.
- CSS is fully waived when the green power is used to make green hydrogen or green ammonia.
Electricity is on the Concurrent List, so each state regulator must issue its own regulations to apply the rules. As of 2025, 21 states and UTs had done so.
Example
A textile unit in Karnataka uses 200 kW of power. Before 2022 it was too small for open access. Now it can sign a long-term contract with a solar developer and get the power through the grid. It pays wheeling charges (the fee for using the lines) and a capped CSS.
Don't confuse with
- Net metering: here a consumer's own rooftop solar sends surplus power to the grid and earns credit against the bill. Under open access, the consumer buys power from an outside generator.
- Renewable purchase obligation (RPO): this is a legal duty to buy a minimum share of renewable power. Open access is one route a consumer can use to buy that power.