ISTS charge waiver
FlashcardsQuick reviseKey facts. One by one.Start →Also called: Inter-State Transmission System waiver · Topic: Infrastructure: Transport, Communications and Energy · NCERT: Beyond NCERT
Meaning
The Inter-State Transmission System (ISTS) is the national network of high-voltage lines that carries electricity from one state to another. Anyone who uses it normally pays ISTS charges, a fee for using these lines. An ISTS charge waiver means the Centre lets some clean-energy projects use this network without paying the fee. This cuts the cost of delivered power. It matters most when the plant is in a sunny or windy state and the buyer is in a different state.
Example
Under the National Green Hydrogen Mission, plants commissioned by 31 December 2030 get an ISTS charge waiver for 25 years. This matters because electricity is the largest cost in making green hydrogen. Pumped storage projects get a 100% waiver if their construction is awarded by 30 June 2028. That waiver also lasts 25 years, counted from the date commercial operation begins (COD).
Don't confuse with
- Open access and wheeling charges: The waiver only removes the fee for inter-state lines. Under open access (the right to buy power from a supplier other than the local DISCOM), states and DISCOMs still control approval. Buyers may still pay wheeling charges for the local network and a cross-subsidy surcharge.
- Award date vs commissioning date: For pumped storage, the 2028 cut-off applies to when construction is awarded. For green hydrogen, the 2030 cut-off applies to when the plant is commissioned.