New Austrian Tunnelling Method
Also called: NATM · Topic: Infrastructure: Transport, Communications and Energy · NCERT: Beyond NCERT
Meaning
The New Austrian Tunnelling Method (NATM) is a way of building tunnels in which the ground itself does part of the job of holding the tunnel up. The tunnel is dug in small steps. After each step, the fresh rock face is quickly supported with shotcrete (concrete sprayed onto the rock) and rock bolts (long steel rods driven into the rock to pin loose layers together). Engineers keep measuring how much the ground moves and add more support where it shifts. It is flexible and cheaper than a full tunnel boring machine, so it suits weak, broken or changing ground, like that of the young Himalaya.
Example
On the Rishikesh–Karnaprayag Rail Project in Uttarakhand, a 110 m triple-track stretch of Tunnel-14 at Portal-1 (Sumerpur) had to pass through loose soil under homes, with only 20–30 m of soil and rock above it. Engineers first stabilised the ground (pre-excavation support). They then dug the large cross-section as a series of smaller headings (multi-drifting). This is NATM-type sequential support. The tunnel's two faces met on 27 November 2026.
Don't confuse with
- Tunnel boring machine (TBM): a large machine that cuts the full circle of the tunnel and fits the lining as it moves forward. NATM digs in stages, by blasting or digging machines, and adjusts the support as it goes. On the same rail project, the 14.8 km T-8 tunnel was dug with a TBM.
- Breakthrough: this only means the two digging faces have met. It is a milestone, not a tunnelling method. Lining, track and systems still have to be put in after it.