Stranded power capacity
Also called: Stranded renewable capacity · Topic: Infrastructure: Transport, Communications and Energy · NCERT: Beyond NCERT
Meaning
Stranded power capacity is a power plant that is ready to run, but its electricity cannot reach buyers or cannot be sold. There are two usual causes. The first is that no transmission line connects the plant to the grid. The second is that no buyer has signed a power purchase agreement (PPA), the long-term contract that fixes the price and supply terms. Money has already gone into the plant, but it earns nothing. This is why grid integration, and not only new generation, decides how fast India's renewable energy grows.
Example
A developer builds a solar park in a renewable energy zone. The line meant to carry away its power is still only at the foundation-stone stage. Some DISCOMs (state electricity distribution companies) will not sign a power sale agreement while the grid connection is still far away, so the power is stranded. The Ministry of Power is relying on a ₹2.4 lakh crore transmission plan and changes to grid-access rules to free up such capacity.
Don't confuse with
- Cancelled grid connectivity: this is the opposite problem. Here the grid access is ready but the plant is late. Since 2022, the Central Transmission Utility has cancelled connectivity for 24 projects totalling 6,343 MW, and the Ministry of Power blames delays by the developers.
- Stranded assets: these are plants, such as coal plants, that lose value early because policy or the energy transition makes them uneconomic. They are not stuck for lack of a line or a buyer.