Meaning

Tariff-based competitive bidding (TBCB) is a way of buying power or storage through an open contest. Developers bid the tariff, meaning the price per unit they will charge the buyer (usually a discom, a power distribution company) over a long contract. The lowest qualifying bid wins. Because the price comes out of competition and not from a regulator working out costs, the process is transparent and standardised, and it tends to push costs down for consumers. The risk is that a bid can be so low that the project later cannot raise a loan or get built.

Example

Suppose three developers bid to supply stored power to a discom at ₹3.1, ₹2.9 and ₹2.8 per unit. The ₹2.8 bidder wins the contract. In February 2025 the Ministry of Power issued TBCB guidelines for buying storage capacity from pumped storage projects. The Union Cabinet's ₹14,500 crore viability gap funding scheme for 92 GWh of grid-scale storage (November 2026) also hands out capacity through TBCB.

Don't confuse with

  • Feed-in tariff: under a feed-in tariff, the government or regulator fixes a guaranteed price in advance. Under TBCB, the price comes from competition among bidders. India replaced feed-in tariffs for solar with competitive reverse auctions.
  • Viability gap funding: viability gap funding is a capital grant that makes a project bankable. TBCB is the method for choosing who builds the project and at what price. The two are often used together.