·PIB·15 marks·250–350 wordsPolityEconomyS&T

Evaluate the Tariff Based Competitive Bidding and BOOM models in transmission. How can State Transmission Utilities' capacity be strengthened to meet targets under GEC-III?

New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →
In this answer
  1. Merits of TBCB–BOOM
  2. Limitations
  3. Strengthening STU Capacity

Green Energy Corridor Phase-III (GEC-III) was approved by the Cabinet in September 2026. It aims to evacuate up to 135 GW of renewable energy through intra-state networks by FY 2032-33. New lines are to be built under Tariff Based Competitive Bidding (TBCB) by private developers on a Build-Own-Operate-Maintain (BOOM) basis [1]. These models work well, but only if State Transmission Utilities (STUs) are capable.

Merits of TBCB–BOOM

  • Price discovery: the bidder quoting the lowest yearly transmission charge wins. This beats the cost-plus approach, where costs simply pass through [1].
  • Private capital: the Centre gives only ₹54,082 crore of the ₹1,86,405 crore outlay. Private Transmission Service Providers fill the gap [1].
  • Lifecycle accountability: the developer owns and maintains the line for the whole contract period. This gives it a reason to build on time and to a good standard.
  • Risk transfer: construction and maintenance risks move off the STU's balance sheet.

Limitations

  • Cost deferred, not removed: distribution companies (discoms) pay the charges over decades. Discoms still make losses because tariffs are set below cost and technical and commercial losses are high [2].
  • Risks the developer cannot manage: right-of-way and land disputes stay with the State. Delays persist: only 58% of the transmission lines targeted for 2024-25 were added [2].
  • Limited scope: it does not suit upgrades of existing lines, so Cost Plus Basis is kept for that work [1].

Verdict: TBCB–BOOM suits new lines. Its results depend on the groundwork STUs do before bidding.

Strengthening STU Capacity

  • Learn from past gaps: only about 26 GW of the 44 GW planned under GEC-I and GEC-II has been connected to the grid [3].
  • Project readiness before bidding: STUs should finish route surveys, forest clearances and right-of-way permissions before inviting bids.
  • Milestone-linked funding: the Centre's share has fallen from 40% in GEC-I to 33% in GEC-II [4] and about 29% in GEC-III [1]. Central money should be released when lines are switched on, not when contracts are signed.
  • Skilled cells: dedicated units for bid management, contract monitoring and grid planning. Congestion data should guide where the 50 GWh of battery storage is placed [1].
  • Discom finances: GEC-III should be paired with the Revamped Distribution Sector Scheme, which takes 60% of the Ministry of Power's 2026-27 spending [2], so that discoms can pay transmission charges.

TBCB–BOOM brings efficiency and private capital, but STUs remain central to delivering GEC-III. Better STU planning, milestone-linked funding and healthier discoms can make GEC-III a model of cooperative federalism. It would then advance India's 900 GW non-fossil target by 2035 [1] and SDG 7 (affordable, clean energy).

Sources

  1. 1Cabinet approves Green Energy Corridor Phase-III scheme for Intra-State Transmission System with BESS (PIB, 30 Sep 2026): 135 GW target, TBCB/BOOM, Cost Plus Basis, outlay, central support, 50 GWh BESS, 900 GW target
  2. 2Demand for Grants 2026-27 Analysis: Power and New & Renewable Energy (PRS Legislative Research): 58% of targeted lines added, reasons for discom losses, RDSS share of spending
  3. 3Implementation of Intra-State Green Energy Corridor Scheme (Lok Sabha Unstarred Question AU2060): about 26 GW of 44 GW connected under GEC-I and GEC-II
  4. 4Cabinet approves Intra-State Transmission System – Green Energy Corridor Phase-II (PIB): 40% central support in GEC-I, 33% in GEC-II
Practice
6 questions on this item
Check the answer for each question, or reveal all at once.
Practice MCQs →

More from this note

More on Polity