"Transmission, not generation, is now the binding constraint on India's renewable transition." Examine with reference to the Green Energy Corridor programme.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
Solar and wind make up 37% of installed capacity but supply only 13% of electricity [1]. Part of this gap is intermittency. Part of it is a grid that cannot carry renewable energy (RE) out of resource-rich States. Transmission, more than new generation, now sets the pace of the transition.
Why transmission is the binding constraint
- Execution lag: only 58% of targeted transmission lines were added in 2024-25 [1].
- Unfinished corridors: GEC-I and GEC-II planned about 44 GW of evacuation across 10 States, but only about 26 GW has been integrated [2]. GEC-I was due in 2022 and slipped [3].
- Curtailment: RE output is forced down in peak solar hours when intra-state lines are congested [4].
- Gestation mismatch: solar parks come up faster than lines, which face right-of-way and land-acquisition hurdles.
How the Green Energy Corridor responds
- GEC-I (8 States, ~24 GW, 40% central assistance) and GEC-II (7 States, ~20 GW, 33%) built dedicated intra-state lines [3].
- An inter-state GEC-II component carries 13 GW from Ladakh [5].
- GEC-III (approved 30 Sep 2026) will evacuate up to 135 GW within States and add 50 GWh of battery storage. Its outlay is ₹1,86,405 crore and the target date is FY 2032-33 [4].
- TBCB and BOOM models bring in private Transmission Service Providers [4].
Constraints beyond transmission
- Storage: a four-hour battery holding 50 GWh can supply about 12.5 GW. That is under a tenth of 135 GW.
- Discom finances: under-priced tariffs and high technical and commercial losses weaken discoms' ability to pay transmission charges [1].
- Falling central share: the Centre funds about 29% in GEC-III, against 40% in GEC-I, so States carry more of the cost [3][4].
Way forward
- Release central support when lines are energised, not when contracts are awarded.
- Settle routes with forest and mining authorities before bidding.
- Plan GEC-III batteries and Viability Gap Funding for storage through one State-wise list of sites [1].
- Pair new corridors with discom reform under RDSS, which takes 60% of the Power Ministry's 2026-27 budget [1].
Transmission has overtaken generation as the tighter constraint, and GEC-III's scale and storage focus recognise this. Delivery on time will need capable STUs, solvent discoms and coordinated storage. That will decide whether India reaches 900 GW of non-fossil capacity by 2035 [4] and meets SDG 7's goal of affordable, clean energy.
Sources
- 1PRS Legislative Research – Demand for Grants 2026-27 Analysis: Power and New & Renewable Energy: 37% capacity vs 13% generation; 58% of line targets met; discom losses; VGF for storage; RDSS share
- 2Implementation of Intra-State Green Energy Corridor Scheme (Lok Sabha Unstarred Question AU2060): ~26 GW integrated out of ~44 GW planned under GEC-I and GEC-II
- 3PIB – Cabinet approves Intra-State Transmission System – Green Energy Corridor Phase-II: GEC-I and GEC-II scope, States and central assistance shares
- 4PIB – Cabinet approves Green Energy Corridor Phase-III scheme for Intra-State Transmission System with Battery Energy Storage Systems (30 Sep 2026): 135 GW, 50 GWh BESS, outlay, TBCB/BOOM, curtailment, 900 GW by 2035
- 5PIB – Cabinet approves Green Energy Corridor (GEC) Phase-II – Inter-State Transmission System for 13 GW RE Project in Ladakh: Ladakh 13 GW inter-state component
Practice
6 questions on this item
Check the answer for each question, or reveal all at once.