India's semiconductor policy has moved from attracting fabs to building the whole ecosystem. Critically examine with reference to Semicon 2.0.
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →In this answer
The Semicon India Programme of 2021 had an outlay of ₹76,000 crore and mainly subsidised fabs and packaging units. Semicon 2.0 was approved in July 2026 with ₹1,27,500 crore spread across six pillars, from design to talent [1]. That is a real shift towards a whole ecosystem, but it is not yet proven in execution.
The shift: from fabs to the ecosystem
- Semicon 1.0 gave fabs 50% fiscal support and approved 12 projects worth over ₹1.64 lakh crore [2].
- Semicon 2.0 has six pillars: Design, Machines and Materials, More Fabs, ATMP/OSAT, R&D and Talent [1].
- Pillar 2 aims to bring in at least 3 equipment makers and 5 chemicals and gases firms. These are the global chokepoints of the chip supply chain [2].
- Pillar 3 widens the fab scope beyond silicon to compound semiconductor, discrete and display fabs [1].
Strengths
- Realistic entry point: 8 of 10 earlier projects were packaging units, which cost far less to set up than fabs [3].
- Design base: startups backed for chip design have completed 16 tape-outs, and 13 have raised venture funding [3].
- Fiscal prudence: incentives are paid only when firms meet agreed milestones, so the state does not pay for plants that are never built [5].
- Time-bound process: a single portal, a 3-year application window and projects of up to 6 years [1][2].
Weaknesses
- Approval is not production: only 5 of 12 Semicon 1.0 projects were producing by October 2026 [2]. Two fab consortia approved in 2013 stalled after approval, and the Empowered Committee had to be reconstituted in 2015 [6].
- Low spending: only 23% (2023-24) and 9% (2024-25) of the semiconductor budget was actually spent [4].
- Headline vs cash: ISM 2.0 got just ₹1,000 crore in 2026-27 [5].
- Spread thin: funding all six pillars at once, while richer economies compete with large subsidies, risks doing many things partly rather than a few things well.
Overall, Semicon 2.0 correctly targets inputs, design and talent rather than fabs alone. Its success depends on phasing: packaging, materials and design first, advanced fabs later. Two steps would help: a public milestone tracker for each project, and partnerships with trusted countries. Together they can turn approvals into output and give real content to Atmanirbhar Bharat in strategic technology.
Sources
- 1Cabinet approves Semicon 2.0 (PIB, 15 Jul 2026)₹1,27,500 crore outlay, six pillars, fab scope, 3-year window and 6-year projects
- 2Union Minister Ashwini Vaishnaw Launches Semicon 2.0 Web Application Portal and Announces 12 Approved Applicants under ECMS (PIB, 06 Nov 2026)Semicon 1.0 outcome (12 projects, ₹1.64 lakh crore, 5 producing), Pillar 2 targets, portal
- 3Semicon India Programme Advances with Approval of 10 Projects (PIB, 2026)2 fabs and 8 packaging units, 16 tape-outs, 13 VC-funded startups
- 4PRS India, Demand for Grants 2025-26 Analysis: Electronics and Information Technology23% and 9% fund utilisation
- 5PRS India, Demand for Grants Analysis 2026-27: MeitYmilestone-linked disbursal, ₹1,000 crore for ISM 2.0 in 2026-27
- 6Reconstitution of Empowered Committee regarding setting up of Semiconductor Wafer Fabrication (FAB) manufacturing facilities in the country (Cabinet decision, Jan 2015)earlier fab approvals that stalled