Trace the procurement cycle from Acceptance of Necessity to contract signature. How can delays in capability induction be reduced?
New · District CollectorCan you hold the district for 72 hours?Floods, a heatwave, an outbreak, a grievance queue. Take the decisions, see the consequences.Play →Under the Defence Acquisition Procedure (DAP) 2020, the Defence Acquisition Council's Acceptance of Necessity (AoN) is where procurement starts, not where it ends [1]. The ₹770 crore LLLR-I radar contract with BEL came about ten months after its AoN [2][3]. That is faster than before, but the cycle still lags threats such as drones.
Procurement cycle: AoN to contract
SQR → AoN (DAC) → RFP → Technical Evaluation → Field Trials
→ Staff Evaluation → CNC → CFA approval → CONTRACT
Capital acquisition cycle under DAP 2020
- AoN: the DAC approves the need, the buy category and an indicative cost. On 29 Dec 2025 it cleared about ₹79,000 crore, including Low Level Light Weight Radars and IDDIS Mk-II [3].
- RFP and technical evaluation: vendors bid against the Services Qualitative Requirements (SQRs), and their offers are checked for compliance.
- Trials: field and staff evaluation follow. DAP 2020 allows Integrated Single Stage Trials for systems designed by DRDO and DPSUs [1].
- Contract: the Contract Negotiation Committee (CNC) settles the price and the Competent Financial Authority (CFA) approves it. The LLLR-I contract was signed on 21 Oct 2026 [2].
Reducing delays in capability induction
- Procedural: extend single-stage AoN, which DAP 2020 allows up to ₹500 crore, and use certification and simulation instead of repeated trials [1]. MoD's 2025 committee under DG (Acquisition) is reviewing DAP 2020 [4].
- Oversight: the Standing Committee on Defence sought a time-bound review of procurement rules [5]. Parliament should track delivery dates, not just signing dates.
- Industrial: domestic firms won 177 of 193 contracts in FY 2024-25 [6]. Buy (Indian-IDDM) orders, such as the Air Defence Fire Control Radars, shorten supply chains [7]. A wider private vendor base would keep one DPSU from becoming a bottleneck.
- Technological: create a fast-track route for counter-drone systems, whose technology changes faster than the procurement cycle.
- Operational: contract sensors and shooters together. LLLR-I and IDDIS Mk-II were cleared in the same AoN, so they should reach units at the same time [3].
Faster AoN-to-contract timelines are necessary, but timely induction is the real measure of success. A reformed DAP with fixed timelines, accountability for delivery and a broad Aatmanirbhar industrial base will let India buy for tomorrow's threats rather than yesterday's.
Sources
- 1Raksha Mantri Shri Rajnath Singh unveils Defence Acquisition Procedure 2020 (PIB)single-stage AoN up to ₹500 crore; Integrated Single Stage Trials; certification and simulation
- 2Centre inks ₹770-crore pact with BEL for low-level radars (The Hindu, 22 Oct 2026)LLLR-I contract value and signing date
- 3DAC clears proposals worth Rs 79,000 crore to enhance the capabilities of the Armed Forces (PIB)29 Dec 2025 AoN for LLLRs and IDDIS Mk-II
- 4MoD Initiates Comprehensive Review of Defence Acquisition Procedure 2020 to Align with National Reforms (PIB)DG (Acquisition) review committee, 2025
- 5Standing Committee on Defence (2024-25), 18th Lok Sabha, 13th Reporttime-bound review of procurement rules
- 6Ministry of Defence: Year End Review 2025 (PIB)177 of 193 FY 2024-25 contracts to domestic industry
- 7Aatmanirbhar Bharat: MoD inks Rs 2,000 crore contract with BEL for Air Defence Fire Control Radars (PIB)Buy (Indian-IDDM) category
Practice
7 questions on this article
Check the answer for each question, or reveal all at once.