Flash Report on Central Sector Infrastructure Projects worth ₹150 crore and above

In this note
  1. At a Glance
  2. Why in the News
  3. Background & Evolution
  4. Core Static Facts
  5. Multi-Dimensional Analysis
  6. Recent Developments (last 12-18 months)
  7. Prelims Hooks
  8. Mains Relevance
  9. Related Topics to Study Next
  10. Common Errors / Trap Areas

1. At a Glance

  • PAIMANA (Project Assessment Infrastructure Monitoring and Analytics for Nation-Building) is MoSPI's web portal tracking Central Sector Infrastructure Projects costing ₹150 crore and above [3].
  • As of June 2026, it monitors 1,847 projects worth ₹40.54 lakh crore total revised cost, with cumulative expenditure of ₹21.97 lakh crore (~54.18%) [1].
  • Relevant for Prelims (numbers, nomenclature, ministry) and Mains GS-III (infrastructure, project implementation, delays/cost overruns).
  • Part of a broader ecosystem with PRAGATI and PM GatiShakti for infrastructure monitoring and course correction [6][8].

2. Why in the News

  • MoSPI released the June 2026 Flash Report, showing PAIMANA now tracks 1,847 projects worth ₹40.54 lakh crore, up from 1,702 projects (₹33.71 lakh crore) as of January 2026 [1][5].
  • Monthly Flash Reports are being published regularly since July 2025, keeping the topic in continuous news cycle [2][4].

3. Background & Evolution

  • PAIMANA officially launched on 25 September 2025, replacing the earlier OCMS-2006 (Online Computerized Monitoring System), which had monitored Central Sector projects of ₹150 crore+ since 2006 [2][4].
  • MoSPI is statutorily mandated to monitor status of ongoing Central Sector infrastructure projects costing ₹150 crore and above [2].
  • Flash Reports generated via the portal have been published from July 2025 onward, available at ipm.mospi.gov.in/ReportPage [2].
  • Timeline of recent Flash Reports: December 2025 → January 2026 (1,702 projects, ₹33.71 lakh crore) → March 2026 → April 2026 → June 2026 (1,847 projects, ₹40.54 lakh crore) [1][5][7].

4. Core Static Facts

Item Detail
Portal name PAIMANA [2]
Full form Project Assessment Infrastructure Monitoring and Analytics for Nation-Building [2]
Nodal Ministry Ministry of Statistics & Programme Implementation (MoSPI) [1]
Threshold Central Sector projects costing ₹150 crore and above [3]
Predecessor system OCMS-2006 [2][4]
Launch date 25 September 2025 [2]
Coverage (June 2026) 1,847 projects, ₹40.54 lakh crore revised cost, across 17 Central Ministries/Departments [1]
Coverage (Jan 2026) 1,702 projects, ₹33.71 lakh crore original cost [5]
Cumulative expenditure (June 2026) ₹21.97 lakh crore (~54.18% of revised cost) [1]
Key ministries covered Road Transport & Highways, Power, Civil Aviation, Petroleum & Natural Gas, Telecommunications, Coal, Railways, Steel, Water Resources/Ganga Rejuvenation, Mines, Housing & Urban Affairs, Ports Shipping & Waterways, Higher Education, Health & Family Welfare, DPIIT [5]
Related mechanism PRAGATI — PM-led periodic video-conference review of stalled projects [6][8]
Related mechanism PM GatiShakti Network Planning Group — separately evaluated 352 projects worth ₹16.10 lakh crore [8]

5. Multi-Dimensional Analysis

Economic

  • Tracks ₹40.54 lakh crore in capital investment — roughly comparable in scale to a full year's Union capital expenditure, making delays/overruns fiscally significant [1].
  • Expenditure utilisation (~54%) signals pace of capital deployment across sectors like power, roads, railways [1].

Administrative / Governance

  • Replaces a two-decade-old system (OCMS-2006) with data analytics-driven monitoring, improving real-time tracking and accountability of 17 ministries [2][4].
  • Enables ministries to be "regularly apprised of their project execution and slippages" for timely intervention — an early-warning/course-correction tool rather than a passive dashboard [6].
  • Works alongside PRAGATI (PM-level review) and PM GatiShakti (multimodal planning), reflecting a layered institutional architecture for infrastructure delivery [6][8].

Technological

  • A "data-driven decision-making" digital platform — part of the broader digital governance push (e-monitoring replacing manual/OCMS reporting) [1][2].

6. Recent Developments (last 12-18 months)

  • 25 Sept 2025: PAIMANA portal launched, replacing OCMS-2006 [2][4].
  • July 2025 onward: Monthly Flash Reports begin publication [2].
  • December 2025 / January 2026: Flash Reports show 1,702 projects, ₹33.71 lakh crore [5][7].
  • March–April 2026: Subsequent monthly Flash Reports published [S1 search context].
  • 28 July 2026: Latest Flash Report — 1,847 projects, ₹40.54 lakh crore, ₹21.97 lakh crore expenditure (54.18%) [1].

7. Prelims Hooks

  • PAIMANA = Project Assessment Infrastructure Monitoring and Analytics for Nation-Building [2].
  • PAIMANA is administered by MoSPI, not NITI Aayog or DPIIT [1].
  • PAIMANA monitors Central Sector projects costing ₹150 crore and above [3].
  • PAIMANA replaced OCMS-2006 (Online Computerized Monitoring System) [2].
  • PAIMANA launched on 25 September 2025 [2].
  • As of June 2026: 1,847 projects worth ₹40.54 lakh crore monitored [1].
  • As of January 2026: 1,702 projects worth ₹33.71 lakh crore [5].
  • Number of Central Ministries/Departments covered: 17 [1][5].
  • Cumulative expenditure as of June 2026: ₹21.97 lakh crore (54.18%) [1].
  • Flash Reports have been published monthly since July 2025 [2].
  • PRAGATI reviews are chaired by the Prime Minister via video conferencing [6].
  • PM GatiShakti Network Planning Group separately evaluated 352 projects worth ₹16.10 lakh crore [8].
  • Ministry of Railways, Power, Road Transport & Highways are among ministries covered under PAIMANA [5].

8. Mains Relevance

  • GS-III: Infrastructure — Energy, Ports, Roads, Airports, Railways etc.; investment models; project implementation and monitoring mechanisms.
  • GS-II: Government policies and interventions for development; issues arising from design and implementation.
  • Possible question stems:
  • "Discuss the significance of real-time monitoring platforms like PAIMANA in addressing time and cost overruns in Central Sector infrastructure projects in India."
  • "How do PAIMANA, PRAGATI, and PM GatiShakti complement each other in India's infrastructure governance architecture? Examine."
  • "Critically evaluate the transition from OCMS to PAIMANA in terms of improving project monitoring outcomes."

9. Related Topics to Study Next

  • PM GatiShakti National Master Plan — multimodal infrastructure planning, directly linked via Network Planning Group [8].
  • PRAGATI (Pro-Active Governance and Timely Implementation) — PM-chaired review mechanism for stalled projects [6].
  • Project Monitoring Group (DPIIT) — earlier institutional mechanism reviewing high-impact projects [8].
  • National Infrastructure Pipeline (NIP) — long-term capital investment planning framework.
  • Capital expenditure trends in Union Budget — fiscal linkage to infrastructure spend.
  • MoSPI's other functions — National Statistical Office, GDP data, National Sample Survey.
  • Public-Private Partnership (PPP) models in infrastructure — financing angle.

10. Common Errors / Trap Areas

  • Confusing PAIMANA (MoSPI, monitoring) with PM GatiShakti (DPIIT/Commerce Ministry, planning) — distinct bodies with overlapping but separate mandates [1][8].
  • Assuming PAIMANA is a NITI Aayog initiative — it is a MoSPI platform [1].
  • Mixing up the ₹150 crore threshold with other scheme thresholds (e.g., CCEA approval limits) — specific to Central Sector project monitoring only [3].
  • Forgetting PAIMANA replaced OCMS-2006, not created monitoring from scratch — the monitoring mandate is decades old, only the digital platform is new [2][4].
  • Conflating project count/cost figures across different months (e.g., citing January 2026 figures as current) — always check report month [1][5].

Sources

  1. 1Flash Report June 2026 (PIB)pib.gov.in · tier 1
  2. 2PAIMANA Web Portalpib.gov.in · tier 1
  3. 3Flash Report on Central Sector Infrastructure Projects worth ₹150 crore and abovepib.gov.in · tier 1
  4. 4Implementation of PAIMANApib.gov.in · tier 1
  5. 5As of January 2026, PAIMANA captures status of 1,702 projectspib.gov.in · tier 1
  6. 6PAIMANA Portal and Management of Major Infrastructure Projectspib.gov.in · tier 1
  7. 7Flash Report January 2026 (MoSPI PDF)ipm.mospi.gov.in · tier 1
  8. 8PM GatiShakti Network Planning Group Evaluates 352 Infrastructure Projects Worth ₹16.10 Lakh Crorepib.gov.in · tier 1

Also on 28 July

All 28 July articles →