What’s ailing India’s battery scheme for EVs?
In this note
Practice
4 questions on this article
Check the answer for each question, or reveal all at once.
UPSC Prelims + Mains Study Note
1. At a Glance
- The Advanced Chemistry Cell Production Linked Incentive (ACC PLI) scheme is India's flagship ₹18,100 crore programme to build a domestic battery manufacturing ecosystem for EVs and renewable energy storage. [1]
- As of early 2026, the scheme is severely underperforming: only 1.4 GWh installed out of a 50 GWh target, barely 1,118 jobs created vs. a projected 10.3 lakh, and only ~25.6% of targeted investment attracted. [5]
- Critical for UPSC: intersects GS-III themes of industrial policy, energy security, import substitution, EV ecosystem, and China dependency.
- The scheme's struggles expose structural weaknesses in India's PLI framework when applied to deep-tech manufacturing with long gestation periods.
2. Why in the News
- A February 2026 analysis by IEEFA (Institute for Energy Economics and Financial Analysis) and JMK Research and Analysis revealed alarming underperformance: target of 50 GWh by 2025 missed catastrophically. [5]
- Of 50 GWh allotted: 1.4 GWh installed, 8.6 GWh "under development" but delayed, and 20 GWh with zero progress. [5]
- Rajesh Exports (one of four original awardees) reportedly exited; Hyundai and Ola Electric have shown limited on-ground progress.
- The Ministry of Heavy Industries (MHI) awarded a fresh 10 GWh capacity to one new bidder in a later round, and signed a Programme Agreement with Reliance New Energy Battery Limited for 10 GWh on 17 February 2025, signalling an attempt to revive the scheme. [3][4]
3. Background & Evolution
| Year | Milestone |
|---|---|
| May 2021 | Cabinet approval: PLI scheme for ACC Battery Storage; outlay ₹18,100 crore [1] |
| October 2021 | Scheme formally launched [5] |
| 2022 | NITI Aayog publishes "Need for ACC Energy Storage in India" reports advocating domestic manufacturing [6] |
| May 2022 | Bidding concluded; 10 bids (~130 GWh) received — strong initial interest [7] |
| July 2022 | 4 companies selected for 50 GWh: Reliance New Energy Solar, Ola Electric, Hyundai Global Motors, Rajesh Exports [2] |
| 2023 | Programme Agreements signed with 3 companies (Rajesh Exports dropped out) [8] |
| 2024 | MHI awards 10 GWh to one additional bidder in supplementary round [3] |
| Feb 2025 | Programme Agreement signed with Reliance New Energy Battery Ltd for 10 GWh [4] |
| 2025 (deadline) | Target of 50 GWh production capacity — missed entirely [5] |
Predecessor context: India's battery imports (primarily from China) account for a significant share of EV component costs; the scheme was designed to mirror the success of the PLI for mobile manufacturing but in a far more capital- and tech-intensive sector.
4. Core Static Facts
- Scheme name: National Programme on Advanced Chemistry Cell (ACC) Battery Storage (PLI)
- Launch: Cabinet approval May 2021; operationalised October 2021
- Outlay: ₹18,100 crore [1]
- Implementing Ministry: Ministry of Heavy Industries (MHI)
- Nodal Agency: MHI (under Department for Promotion of Industry and Internal Trade ecosystem)
- Total Capacity Target: 50 GWh (main) + 5 GWh "Niche" ACC [1]
- Incentive structure: Set-up within 2 years; incentives disbursed over 5 years on domestic sales [1]
- Technology stance: Technology-agnostic — higher incentives for superior technologies [1]
- Eligible chemistries: Lithium-ion (Li-ion), Nickel Manganese Cobalt (NMC), Lithium Iron Phosphate (LFP), Sodium-ion [5]
- Original awardees (4): Reliance New Energy Solar Ltd, Ola Electric Mobility Pvt Ltd, Hyundai Global Motors Co. Ltd, Rajesh Exports Ltd [2]
- Jobs target: ~10.3 lakh (1.03 million); actual: 1,118 (~0.12% of target) [5]
- Investment attracted: ~25.58% of target [5]
- Expected import savings: ₹2,00,000–2,50,000 crore over programme period [1]
- ACCs defined as: New-generation storage technologies converting chemical energy ↔ electric energy; broader than conventional lead-acid batteries [1][5]
5. Multi-Dimensional Analysis
Economic
- Scheme premised on import substitution: India imports near-100% of battery cells, predominantly from China, raising EV costs and widening the current account deficit. [1][5]
- PLI incentives are sales-linked, not capex-linked — this creates a chicken-and-egg problem: manufacturers must invest heavily before receiving any incentive, deterring risk-averse capital in an unproven tech segment. [5]
- Only 25.58% of targeted investment attracted; job creation at 0.12% of target signals a failure of the PLI model for deep-tech manufacturing with long gestation cycles. [5]
- Projected savings of ₹2–2.5 lakh crore in oil import bills remain theoretical. [1]
Scientific / Technological
- Battery cell manufacturing requires gigafactory-scale investment, proprietary chemistry knowledge, and global supply chains for critical minerals (lithium, cobalt, nickel, manganese) — not easily replicable via fiscal incentives alone. [5][6]
- India lacks upstream critical mineral security (no significant lithium/cobalt domestic reserves); this is a structural barrier the PLI does not address. [6]
- The scheme's technology-agnostic design, while flexible, may have diffused investment focus across too many chemistries. [1][5]
- Sodium-ion batteries are emerging as a lower-cost alternative but are at early commercial stage globally.
Geopolitical / Strategic
- Reducing dependence on Chinese battery imports is an explicit geopolitical objective — China dominates ~75–80% of global battery cell manufacturing. [5]
- Failure of the scheme reinforces China's leverage over India's EV transition and clean energy ambitions under the Paris Agreement/NDC targets.
- India's PLI for solar PV modules faces similar import-substitution challenges, making this a systemic concern in industrial policy.
Environmental
- Without domestic battery manufacturing, India's EV adoption remains import-dependent and thus environmentally fragile in supply chain terms.
- Battery manufacturing involves hazardous chemical processes and end-of-life disposal risks — a domestic ecosystem requires simultaneous battery recycling regulations (not yet robust).
- Delay in EV battery production directly slows India's emission reduction trajectory under NDC commitments (net-zero by 2070). [6]
Administrative / Governance
- Rajesh Exports' exit and delays by Ola Electric and Hyundai reveal weak due diligence in awardee selection — market credibility vs. manufacturing capability mismatch.
- The 2-year setup window is grossly inadequate for gigafactory-scale battery plants (global benchmark: 3–5 years for greenfield facilities).
- Absence of demand-side aggregation (no guaranteed offtake by government fleets/DISCOMS) undermines the business case for awardees.
- Scheme lacks milestone-based accountability with enforceable exit clauses and performance bonds.
Legal / Constitutional
- Implemented under the broader PLI framework (Cabinet Decision, May 2021); no dedicated statute — relies on executive/administrative order.
- Incentive disbursement rules governed by Programme Agreements (bilateral contracts between MHI and awardees) — disputes would fall under contract law/arbitration, not a sector-specific regulatory body.
6. Recent Developments (Last 12–18 months)
- 17 February 2025: Programme Agreement signed between MHI and Reliance New Energy Battery Ltd for 10 GWh capacity under ACC PLI. [4]
- 2024: MHI awarded 10 GWh capacity to one new bidder in a supplementary round after original awardee(s) faltered. [3]
- February 2026: IEEFA + JMK Research report publicly quantifies scheme's failure — only 1.4 GWh installed, 8.6 GWh delayed, 20 GWh stalled. [5]
- 2025 (missed deadline): The scheme's original 50 GWh target year passed with less than 3% capacity realised.
- Ongoing parliamentary questions (PIB, 2024–25) reveal MHI's acknowledgment of delays and revised timelines. [9]
7. Prelims Hooks
- The ACC PLI scheme was approved by the Union Cabinet in May 2021 with an outlay of ₹18,100 crore. [1]
- The scheme targets 50 GWh of ACC manufacturing capacity + 5 GWh of Niche ACC. [1]
- Implementing Ministry: Ministry of Heavy Industries (MHI), not MNRE or MoP. [1]
- The scheme is technology-agnostic — open to Li-ion, NMC, LFP, and sodium-ion chemistries. [1][5]
- Four original awardees: Reliance New Energy Solar, Ola Electric, Hyundai Global Motors, Rajesh Exports. [2]
- Incentive structure: manufacturing facility set up in 2 years; incentives paid over 5 years on domestic sales. [1]
- As of early 2026, only 1.4 GWh installed — less than 3% of the 50 GWh target. [5]
- Jobs created: 1,118 — approximately 0.12% of the 1.03 million targeted. [5]
- Expected savings on oil imports from ACC PLI success: ₹2–2.5 lakh crore. [1]
- A Programme Agreement with Reliance New Energy Battery Ltd for 10 GWh was signed on 17 February 2025. [4]
- Total bids received in the original bidding round: 10 bids aggregating ~130 GWh — nearly 2.6× the 50 GWh on offer. [7]
- ACC stands for Advanced Chemistry Cell — stores electric energy as chemical energy and reconverts it. [1][5]
- Investment attracted under the scheme as of early 2026: approximately 25.58% of target. [5]
- The scheme's analysis was published by IEEFA and JMK Research and Analysis (not government bodies). [5]
8. Mains Relevance
GS Paper: Primarily GS-III (Indian Economy — industrial policy, energy, technology); secondary GS-II (governance, policy implementation)
Syllabus headings:
- GS-III: Infrastructure: Energy, Ports, Roads, Airports, Railways; Growth and Development; Government Budgeting; Effects of Liberalization on the Economy; Industrial Policy
- GS-II: Government Policies and Interventions; Implementation of Policies
Plausible Mains Questions:
- "The Production Linked Incentive (PLI) model, while successful in mobile manufacturing, faces structural limits in deep-technology sectors. Critically examine with reference to the ACC battery scheme." (GS-III)
- "India's EV ambitions are constrained by its dependence on Chinese battery imports. Analyse the challenges facing the domestic battery manufacturing ecosystem and suggest a policy roadmap." (GS-III)
- "Evaluate the design and implementation failures of the ACC PLI scheme and discuss what governance reforms could make PLI instruments more effective for capital-intensive industries." (GS-II/III)
9. Related Topics to Study Next
| Topic | Connection |
|---|---|
| PLI Schemes (Overall) | ACC PLI is one of 14 PLI schemes; understanding the broader framework helps compare sector-specific performance. |
| Critical Minerals Mission | Battery manufacturing depends on lithium, cobalt, nickel — India's critical mineral strategy is a direct upstream enabler. |
| FAME Scheme (FAME-II / FAME-III) | Demand-side EV incentive; without which the market for domestically-made batteries is thin. |
| National Electric Vehicle Policy 2024 | Sets EV penetration targets that depend on ACC PLI delivering affordable batteries. |
| Battery Waste Management Rules | End-of-life battery disposal regulation — necessary complement to domestic manufacturing. |
| India's NDCs and Net-Zero 2070 | EV battery ecosystem is central to India's transport decarbonisation commitments. |
| China's dominance in clean tech supply chains | Geopolitical context: China controls ~75% of global battery cell capacity — core to understanding import dependency. |
| Production Linked Incentive for Solar PV Modules | Parallel case of import substitution PLI in clean energy; similar implementation challenges. |
10. Common Errors / Trap Areas
- Wrong Ministry: Aspirants confuse MHI (implementing ministry) with MNRE (Ministry of New and Renewable Energy) or MoP (Ministry of Power). ACC PLI is under MHI.
- Confusing targets: The main target is 50 GWh + 5 GWh Niche — do not quote 55 GWh as a single figure without qualification.
- Mixing up PLI schemes: There are 14 PLI schemes; ACC PLI (₹18,100 crore) is distinct from PLI for White Goods, Solar PV, or Auto/Auto Components — which are also MHI schemes but with different outlays and targets.
- "Technology-specific" trap: The scheme is explicitly technology-agnostic — a common wrong option in MCQs that claim it is restricted to lithium-ion.
- Overstating awardee numbers: Originally 4 companies selected, but one (Rajesh Exports) effectively exited — current active awardees are fewer; Reliance joined later via a separate round.
- Confusing IEEFA with a government body: IEEFA is an independent research organisation, not a government/statutory body — facts from its 2026 report are analytical, not official government data.
Sources
- 1Cabinet approves PLI scheme "National Programme on Advanced Chemistry Cell Battery Storage"pib.gov.in · tier 1
- 2Allotment made for 50 GWh to 4 successful bidders under ACC PLIpib.gov.in · tier 1
- 3MHI awards 10 GWh capacity to one bidder under PLI ACC schemepib.gov.in · tier 1
- 4Programme Agreement signed with Reliance New Energy Battery Limited for 10 GWhpib.gov.in · tier 1
- 5"What's ailing India's battery scheme for EVs?" — Jacob Koshy, The Hindu BusinessLine, 1 February 2026 (article excerpt provided as primary source)tier 4
- 6Need for Advanced Chemistry Cell Energy Storage in India (Part II) — NITI Aayogniti.gov.in · tier 1
- 710 bids (~130 GWh) received under ACC PLIpib.gov.in · tier 1
- 8Three Companies signed Programme Agreement under ACC PLIpib.gov.in · tier 1
- 9Advanced Chemistry Cell Batteries and Domestic Capacity (Parliamentary Q&A)pib.gov.in · tier 1
At the end · practice MCQs
4 questions on this article
Check the answer for each question, or reveal all at once.